MC-Series System Installation & Testing 
Scheduled and Unscheduled Maintenance 
RadioFrame Networks, Inc.
  
99 
Using the breaker on the PDU, turn up each RF Shelf and then verify that each RF Shelf is 
operational before proceeding. The POWER and ALARM LEDs on the front of the RF Shelf 
will light green. 
Complete the procedures in sections 5.4, 5.5 and 5.6. 
7.9.2.2 AIC 
Power down RFN equipment in the following order using circuit breakers on the PDU: 
• 
BIC 
• 
AIC 
• 
RBS 1 (power down RBS 2 and RBS 3 if they are present) 
• 
RF Shelves 1,2 and 3 
 
Disconnect cabling from the back of the chassis to be replaced. 
Refer to Appendix C Cabling Diagrams: 3-Sector Configuration and Appendix D Cabling 
Diagrams: Omni Configuration. 
For the AIC, disconnect the following cabling from the rear of the AIC only: 
Index 
Part Number 
Disconnect From 
To 
Type 
P_12 
820-0614-10 
AIC:  power 
PDU:  AIC 
power 
G_13 
820-0609-00 
AIC:  ground 
GND BAR 
ground 
DAT_1 
111-0566-00 
AIC:  ERTM PORT 1 
RBS 1:  10/100 RFN A 
UTP 
DAT_2 
111-0566-00 
AIC:  ERTM PORT 2 
RBS 1:  10/100 RFN B 
UTP 
DAT_3 
111-0566-00 
AIC:  ERTM PORT 3 
RBS 1:  10/100 RFN C 
UTP 
DAT_5 
111-0565-00 
AIC:  ERTM PORT 4 
BIC:  ERTM PORT 2 
UTP 
 
Remove the chassis from the rack, and package it for shipment. 
Remove the 4 front mounting screws (shown with arrows). 
 
Figure 32 
Front view of AIC 
   
aBPC
PC
  
AIC 
 
CRIC