Chapter 3 Equipment Installation
4. Ensure that cabinet surface is clean and tidy and covered well
by oil paint. All parts of the cabinet are completed and all
markings on the cabinet are correct, clear and complete.
On-site Environment Inspection Items
Check whether redundant goods on site are cleared out and make
sure no binding tape, waste carton, waste cable and plastic bag
left.
Make sure that the installation site is neat and tidy.
Power-on
Prerequisites
1. Power supply voltage accords with ZXMBW E9230 require-
ments.
2. Connect the cabinet power and grounding cable properly.
3. The power switch is disconnected.
Steps
1. There is no power switch located at the ZXMBW E9230 cabi-
net. Therefore, opening external power switches will power on
ZXMBW E9230.
2. During power-on process, if abnormal phenomenon occurs,
disconnect the power switch immediately and find the source
of problem.
E
ND OF STEPS
Confidential and Proprietary Information of ZTE CORPORATION