ZXMBW RA25 Agile 2.5G Remote Radio Frequency Unit Installation Manual 
 
70      
Confidential and Proprietary Information of ZTE CORPORATION 
 
Chassis Installation Check 
The chassis installation position  must  match that on the 
design drawing. 
The chassis must be installed securely, meeting the level 7 
earthquake-resistant requirement.  
The horizontal and vertical deviation of the chassis must be 
less than 3 mm. 
The surface must be clean and the paint must be in good 
condition. No part must fall off or get damaged. Signs on the 
chassis must be correct, clear and complete.  
The inside of the chassis must be clean. The corners inside 
the chassis must be free from messes such as metallic scraps 
and wires.  
All bolts must be tightened. No plain washer or spring 
washer is placed in reverse.