Prepare Gateway for Installation 
Remove all cardboard and packing materials from inside the shelter. 
Connect the battery
The Gateway is shipped with one battery cable (the red, or positive cable) 
disconnected to prevent battery drain. Connect the red cable to the red terminal.
IMPORTANT: When putting your Gateway into cold storage, disconnect the red cable.
Power Up 
Note: 
Register your Gateway online and wait 5 to 10 minutes BEFORE you power it up to 
avoid a delay in uploading data. If you already powered up before registering, 
remove power, register, then repower.
1. Plug the main power cable back into the jack. You should hear two beeps. 
The Gateway will now begin to acquire both the radio signal from the weather 
station as well as the cell signal. You will be able to observe this by watching 
the LED lights.
Main power jack
Main power cable