HP Performance Optimized Data Center (POD) 40c Guida All'Installazione Rapida
Appendix B: Preparing for delivery 33
Item Description
Sign-off
28
Verify the location of the EPO system external to the
powerhouses, if applicable.
29
Verify the location of the remote electronic monitoring system.
30
Verify that tie-downs and other AHJ-required facilities for the HP
POD 40c G2 and power containers are complete at least one
week prior to arrival of HP-provided equipment.
General water supply
Item Description
Sign-off
1
Verify that the site drainage is complete, and the HP POD 40c
G2 is not in a drainage path or flood prone area. HP
recommends placing the HP POD 40c G2 on a raised site pad
recommends placing the HP POD 40c G2 on a raised site pad
to prevent water from entering the HP POD 40c G2.
2
Verify that the humidification water quality meets or exceeds
these standards, which are essentially drinking water
standards.
3
Verify the humidification water supply isolation valve is
installed for each POD.
installed for each POD.
Chilled water system
Item Description
Sign-off
1
Verify the chilled water supply and return headers are
accessible, in the appropriate location, and 100 cm (4 in) in
accessible, in the appropriate location, and 100 cm (4 in) in
diameter.
2
Verify that the chilled water supply temperature meets the
minimum POD chilled water supply temperature of 10°C
(50°F).
3
Verify that a sufficient chilled water flow rate is available.
4
If necessary, verify that the customer-required chilled water
return temperatures can be attained.
return temperatures can be attained.
Power requirements
Item Description
Sign-off
1
Verify that the short circuit analysis, arc flash, and circuit
breaker coordination studies are complete. Verify power work
breaker coordination studies are complete. Verify power work
is completed according to the approved conduit routing
drawings that show the exact routes, plan view, sections, and
elevations.
2
Verify that temporary site power for installation and
construction is planned and available, if applicable.
construction is planned and available, if applicable.
3
Verify that adequate site power exists per the HP POD 40c G2
requirements.
requirements.
General
Item Description
Sign-off
1
Verify the utility connection to the HP POD 40c G2 and any
required metering equipment.
required metering equipment.
2
Verify the third-party commissioning services that might be
required by the owner.
required by the owner.