Appendix B: Preparing for delivery  33 
Item  Description 
Sign-off 
28 
Verify the location of the EPO system external to the 
powerhouses, if applicable. 
 
29 
Verify the location of the remote electronic monitoring system.   
30 
Verify that tie-downs and other AHJ-required facilities for the HP 
POD 40c G2 and power containers are complete at least one 
week prior to arrival of HP-provided equipment. 
 
 
General water supply 
 
Item  Description 
Sign-off 
Verify that the site drainage is complete, and the HP POD 40c 
G2 is not in a drainage path or flood prone area. HP 
recommends placing the HP POD 40c G2 on a raised site pad 
to prevent water from entering the HP POD 40c G2. 
 
Verify that the humidification water quality meets or exceeds 
these standards, which are essentially drinking water 
standards. 
 
Verify the humidification water supply isolation valve is 
installed for each POD.  
 
 
Chilled water system 
 
Item  Description 
Sign-off 
Verify the chilled water supply and return headers are 
accessible, in the appropriate location, and 100 cm (4 in) in 
diameter. 
 
Verify that the chilled water supply temperature meets the 
minimum POD chilled water supply temperature of 10°C 
(50°F). 
 
Verify that a sufficient chilled water flow rate is available.  
 
If necessary, verify that the customer-required chilled water 
return temperatures can be attained. 
 
 
Power requirements 
 
Item  Description 
Sign-off 
Verify that the short circuit analysis, arc flash, and circuit 
breaker coordination studies are complete. Verify power work 
is completed according to the approved conduit routing 
drawings that show the exact routes, plan view, sections, and 
elevations. 
 
Verify that temporary site power for installation and 
construction is planned and available, if applicable. 
 
Verify that adequate site power exists per the HP POD 40c G2 
requirements. 
 
 
General 
 
Item  Description 
Sign-off 
Verify the utility connection to the HP POD 40c G2 and any 
required metering equipment. 
 
Verify the third-party commissioning services that might be 
required by the owner.