insul-lam
Insul-Lam is used as a non-structural nail base
in either a one or two layer system.
in either a one or two layer system.
two-layer system – Begin by installing the
2x dimensional lumber dam around the
perimeter of the roof. The height of the dam
is determined by the depth of Insul-Lam being
installed. In residential applications, PBS
recommends the use of a vapor retarder with
either the one or two layer systems. You
will need to cut one 2’ x 4’ foam section
and enough 2’ x 8’ foam sections from your
shipment to ring the perimeter flush to your
lumber dam.
2x dimensional lumber dam around the
perimeter of the roof. The height of the dam
is determined by the depth of Insul-Lam being
installed. In residential applications, PBS
recommends the use of a vapor retarder with
either the one or two layer systems. You
will need to cut one 2’ x 4’ foam section
and enough 2’ x 8’ foam sections from your
shipment to ring the perimeter flush to your
lumber dam.
Once the 2’ sections are in place, layout the
remaining 4’ x 8’ foam sheets.
remaining 4’ x 8’ foam sheets.
top layer – Apply the nail base top layer
perpendicular to the foam layer so that joints
overlap. You will need to remove 1 1/2” of
foam along the edges of your perimeter course
so the OSB overlaps your lumber dam. Once
an Insul-Lam top sheet is in position, fasten the
assembly to the deck with Premier Panel Screws
following the spacing and frequency determined
by engineering. Penetrate the structural deck
to a depth of at least 1”. Along the perimeter
perpendicular to the foam layer so that joints
overlap. You will need to remove 1 1/2” of
foam along the edges of your perimeter course
so the OSB overlaps your lumber dam. Once
an Insul-Lam top sheet is in position, fasten the
assembly to the deck with Premier Panel Screws
following the spacing and frequency determined
by engineering. Penetrate the structural deck
to a depth of at least 1”. Along the perimeter