Land Pride RCPM2660 Manuale Utente

Pagina di 52
15
Section 1: Assembly & Set-up
12/16/08
RCP2660, RCPM2660, RCP3060 and RCPM3060 Parallel Arm Rotary Cutter   316-111M
Land Pride
PTO Hook-up
Maximum PTO driveline Movement
Figure 1-5
Check Driveline Minimum Length
Refer to Figure 1-6:
1.
Start tractor and slowly engage 3-point controls to
move lower arms until the PTO shaft for the speed
increaser is aligned and level with tractor PTO shaft.
Securely block cutter in this position.
2.
Place tractor gear selector in park, shut tractor
engine off, set park brake and remove switch key.
3.
Attach driveline to cutter and tractor as follows:
a. Slide inner yoke of driveline over speed increaser
shaft and secure with locking collar.
b. Slide outer yoke of driveline over tractor PTO
shaft and secure with locking collar.
c. Skip to step 5 if driveline fits between tractor and
speed increaser. if driveline does not fit, continue
with step 4 below.
4.
The driveline will require shortening if it is too long to fit
between tractor and speed increaser. Shorten
driveline as follows:
IMPORTANT: Do not engage tractor PTO until
driveline is fully connected and hydraulic fluid has
been added to the cutter reservoir.
IMPORTANT: A quick hitch may be used, but is not
recommended because it moves the cutter deck
back about 5" and impedes operator visibility.
IMPORTANT: Refer to Figure 1-5: Avoid premature
driveline breakdown. A rotating driveline must not
exceed
 an angle of 25 degrees up or down.
24872
IMPORTANT: Always check driveline minimum
length during initial setup, when connecting to a
different tractor and when alternating between using
a quick hitch and a standard 3-point hitch. More than
one driveline may be required to fit all applications.
IMPORTANT: It is necessary to aligning the tractor’s
PTO shaft level with the Rotary Cutter’s speed
increaser shaft when checking driveline minimum
length. Too long a driveline can damage tractor,
gearbox and driveline.
a. Make sure cutter and tractor PTO shafts are level
with each other and cutter deck is securely
supported at this height with support blocks.
b. Pull driveline apart into two sections as shown in
Figure 1-6.
c. Attach outer driveline universal joint to tractor
PTO shaft and inner driveline universal joint to the
speed increaser shaft. Pull on each driveline
section to be sure universal joints are secured.
d. Hold driveline sections parallel to each other to
determine if they are too long. The inner and outer
shields on each section should end approximately
1" short of reaching the universal joint shield on
the adjacent section (see “B” dimension). If they
are too long, measure 1" (“B” dimension) back
from the universal joint shield and make a mark at
this location on the inner and outer shields.
e. Cut off inner shield at mark (“X” dimension). Cut
same amount off inner shaft (“X1” dimension).
Repeat cut off procedure (“Y” & “Y1” dimensions)
to outer driveline half.
f. Remove all burrs and cuttings.
Shortening PTO Driveline Shields and Shafts
Figure 1-6
5.
Apply multi-purpose grease to the inside of the outer
driveline shaft and reassemble the two shafts.
6.
Attach inner driveline yoke to speed increaser shaft
and outer driveline yoke to tractor PTO shaft.
7.
Move driveline back and forth to insure that both
ends are secured. Reattach any end that is loose.
8.
Hook the 1st safety chain in the hole on the outer
driveline yoke shield and its opposite end to the
tractor.
9.
Hook the 2nd safety chain in the hole on the inner
driveline yoke shield and the opposite end to the
cutter.
10. Start tractor and raise cutter just enough to remove
support blocks used in step 4 on page 15.
11. Slowly engage tractor’s 3-point controls to lower
cutter. Check for sufficient drawbar clearance. Move
drawbar ahead, aside or remove if required.
IMPORTANT: Two small chains supplied with the
driveline must be attached to restrict shield rotation.