Pre-installation: at the site
Installing and Configuring the Avaya S8400 Media Server
February 2006
13
 
Pre-installation: at the site
Before beginning the installation, verify that you have all the equipment on site by comparing 
the list of items ordered against the items in the boxes. Your project manager can supply you 
with an inventory list. Do not rely solely on the packing slips inside the boxes.
The pre-installation team should have done the following tasks. If they were not all done, do not 
continue with the installation.
Verify that the open, customer-supplied, EIA-310D (or equivalent) standard 19-in. (48-cm) 
4-post equipment rack(s) is(are) properly installed and solidly secured. Make sure that the 
screws that come with the racks are there. If using a rack cabinet, make sure it has 
adequate ventilation.
Verify that the rail kit to support the media server is available for installation.
Verify that the rail kit, required to support the very heavy UPS, is installed on the rack or 
available for installation. For information on installing the rails, see the documentation that 
comes with the rail kit.
Verify that the equipment rack(s) is(are) grounded per local code. See Job Aid: Approved 
Grounds 
(555-245-772).
Verify that the customer provides AC power to the rack from a nonswitched outlet.
Verify that cabling between the TN8400AP and the TN8412AP (SIPI) circuit packs is in 
place.
Equipment specifications
The S8400 Media Server control network components consist of a G650 Media Gateway with a 
TN8400AP circuit pack installed in slot 2, a TN8412AP (SIPI) installed in slot1, and one UPS. 
See 
Table 1: Control network components specifications 
Component
Dimensions
English (in.)
Metric (cm)
U (height)
Weight (lb/kg)
Media Gateway:
G650
14h x 17.5w x 22d
30h x 56w x 48d
8
39/18
UPS:
700 VA
1500 VA
3.5h x 17w x 19d
3.5h x 17w x 24d
9h x 43w x 48d
9h x 43w x 61d
2
2
34/15
50/23