Energy Tech Laboratories F3 ユーザーズマニュアル

ページ / 52
2
f.  If burner operates as described, relay is good. If 
not, install new relay.
CAD CELL TEST (see Figure 27)
g.  Open line switch. Clean cell face and see that 
cell is securely in socket. Reconnect leads. Reset 
safety switch.
h.  Close line switch. If burner starts and runs 
beyond safety switch cut-out time, cell is good. 
If not, install new cell.
3.  WARNING — Check High Limit Control 
— Jumper Thermostat Terminals. Allow burner to 
operate until shut-down by limit. Installation is not 
considered complete until this check has been made.
 
REMOVE JUMPER.
4.  Check low water cut off control with water level at 
normal water line (see Figures 1C and 1D). Raise 
thermostat setting to allow burner to operate. Open 
boiler drain to allow water level to drop to bottom 
of sight glass until burner operation is shut-down by 
low water cut-off.
  Close boiler drain and refill to normal water line. 
Burner should automatically restart during fill. 
Lower thermostat setting.
5.  CHECK OPERATING CONTROL on boiler 
equipped with tankless heaters. With burner off, 
draw hot water until burner starts, then turn off hot 
water and check burner shut-down.
 
IF CONTROLS DO NOT MEET REQUIREMENTS 
AS OUTLINED ABOVE, REPLACE CONTROL AND 
REPEAT CHECK-OUT PROCEDURES.
and readjust oil pressure.  If dripping or after burn 
persist replace fuel pump.
K.
  TEST CONTROLS.
WARNING
Before  installation  of  the  boiler  is  considered 
complete, the operation of all boiler controls must 
be  checked,  particularly  the  primary  control  and 
high limit control.
1.  CHECK THERMOSTAT OPERATION.  Raise and 
lower thermostat setting as required to start and stop 
burner.
2.  VERIFY PRIMARY CONTROL SAFETY 
FEATURES using procedures outlined in 
Instructions furnished with control or instructions as 
follows:
CHECKOUT PROCEDURE
a.  Check wiring connections. Close line switch. 
Check power at control.
PRIMARY RELAY TEST
b.  Disconnect cad cell leads from quick connects 
on underside at primary control. Reset safety 
switch.
c.  Set controller to call for heat. Burner should 
start.
d.  Jumper the quick connect terminals within 15 to 
30 seconds. Burner should run.
e.  Remove the quick connect terminals jumper. 
Burner shuts down in approximately 15 to 60 
seconds.