Table 7. Site Configurable Jumper Options.
a
Pilot Valve /First Stage Oil Valve (Valve/Start) Terminal 21.
b
A 30 second MFEP can be accomplished by adding a jumper wire between Terminals 19 and 5.
SERVICE NOTE:Clipping and removing a site-configurable jumper enhances the level of safety.  Removal after 200 hours of 
main valve operation will result in a hard lockout, Code 110.
STATIC CHECKOUT
After checking all wiring, perform this checkout before 
installing the RM7800/RM7840 on the subbase. These tests 
verify the Q7800 Wiring Subbase is wired correctly, and the 
external controllers, limits, interlocks, actuators, valves, 
transformers, motors and other devices are operating 
properly. 
WARNING
Explosion and Electrical Shock Hazard.
Can cause serious injury, death  or equipment 
damage.
1. Close all manual fuel shutoff valve(s) before starting 
these tests. 
2. Use extreme care while testing the system. Line 
voltage is present on most terminal connections 
when power is on.
3. Open the master switch before installing or 
removing a jumper on the subbase. 
4. Before continuing to the next test, be sure to 
remove test jumper(s) used in the previous test. 
5. Replace all limits and interlocks that are not 
operating properly. Do not bypass limits and 
interlocks.
CAUTION
Equipment Damage Hazard.
Improper testing can damage equipment.
Internal surge protectors can break down and conduct 
a current, causing the RM7800/RM7840 to fail the 
dielectric test or possibly destroy the internal lightning 
and high current protection. Do not perform a dielectric 
test with the RM7800/RM7840 installed.
Equipment Recommended
1. Voltmeter (1M ohm/volt minimum sensitivity) set on the 
0-300 Vac scale. 
2. Two jumper wires; no. 14 wire, insulated, 12 inches 
(304.8 mm) long with insulated alligator clips at both 
ends. An ammeter may be used in place of a jumper 
wire to check the amp usage when testing the blower 
motor, ignition, pilot and main valve operation.
General Instructions
1. Perform all applicable tests listed in Static Checkout, 
Table 8, in the order listed. 
2. Make  sure all manual fuel shutoff valve(s) are closed.
3. Perform only those tests designated for the specific 
RM7800/RM7840 model being tested. 
4. Raise the setpoint of the operating controller to simulate 
a call for heat. 
5. For each test, open the master switch and install the 
jumper wire(s) between the subbase wiring terminals 
listed in the Test Jumpers column.
6. Close the master switch before observing operation. 
7. Read the voltage between the subbase wiring terminals 
listed in the Voltmeter column.
8. If there is no voltage or the operation is abnormal, check 
the circuits and external devices as described in the last 
column. 
9. Check all wiring for correct connections, tight terminal 
screws, correct wire, and proper wiring techniques. 
Replace all damaged or incorrectly sized wires. 
10. Replace faulty controllers, limits, interlocks, actuators, 
valves, transformers, motors and other devices as 
required. 
11. Make sure normal operation is obtained for each 
required test before continuing the checkout. 
12. After completing each test, be sure to remove the test 
jumper(s). 
WARNING
Explosion Hazard. 
Can cause serious injury or death.
Make sure all manual fuel shutoff valves are closed 
before performing static checkout.
Jumper Number
Description
Intact
Clipped
RM7800/RM7840 Type
JR1
Pilot Flame Establishing 
Period (PFEP)
10 seconds
4 seconds
All
JR2
Pilot Valve
a
/Main Flame 
Establishing Period (MFEP)
10 seconds
Intermittent
15 or 30 seconds Interrupted
b
RM7800G/RM7840G
JR3
Start-up Interlock Check
Disabled
Enabled
All