Cable Ductwork 
Page C-5
 
C
Table C-2.
Installation Sequence 
Step
Group
Remarks
1
41
Install basic ductwork on each cabinet
2
51
Install cross-aisle shielded ductwork
3
10 or 26
Install I/O cross-aisle or cabinet to wall cable trough
22-25
Install I/O cross-aisle to wall trough duct
4
8
or
9
Install I/O cable rack coupling to rear of cabinet
or
install I/O cable rack riser to end of cabinet
5
12-19,
21, 32,
34, & 35
Install AC power ducts
6
27
Install shielded cable ducts between DEFINITY and 
DIMENSION cabinets
7
28
Install I/O cable ducts between DEFINITY and 
DIMENSION cabinets
8
29 & 31
Install shielded duct assembly from front of system 
cabinet to rear of a DEFINITY cabinet (group 29) or 
front of a DEFINITY cabinet to rear of system cabinet 
(group 31)
9
30
I/O transition assembly for cross-aisle (DEFINITY)
10
33
Ladder rack supported 86 or 88.5 inches (218.4 cm 
or 224.8 cm) from floor
Continued on next page