GENERAL INFORMATION
sEctioN 1.2
iNstallatioN Basics
introduction
Information  in  this  section  is  provided  so  that  the 
service  technician  will  have  a  basic  knowledge  of 
installation  requirements  for  home  standby  systems. 
Problems that arise are often related to poor or unau-
thorized installation practices.
A  typical  home  standby  electric  system  is  shown  in 
Figure  1  (next  page).  Installation  of  such  a  system 
includes the following:
•  Selecting a Location
•  Grounding the generator.
•  Providing a fuel supply.
•  Mounting the load center.
•  Connecting power source and load lines.
•  Connecting system control wiring.
•  Post installation tests and adjustments.
SelectinG a location
Install  the  generator  set  as  close  as  possible  to  the 
electrical  load  distribution  panel(s)  that  will  be  pow-
ered by the unit, ensuring that there is proper ventila-
tion for cooling air and exhaust gases. This will reduce 
wiring  and  conduit  lengths.  Wiring  and  conduit  not 
only add to the cost of the installation, but excessively 
long wiring runs can result in a voltage drop.
Control system interconnections between the transfer 
switch and generator consist of N1 and N2, and leads 
23,  15B  and  0.  Control  system  interconnection  leads 
must be run in a conduit that is separate from the AC 
power leads. Recommended wire gauge size depends 
on the length of the wire:
max. cable length
recommended Wire size
35 feet (10.67m)
No. 16 AWG.
60 feet (I8.29m)
No. 14 AWG.
90 feet (27.43m)
No. 12 AWG.
GroundinG the Generator
The  National  Electric  Code  requires  that  the  frame 
and  external  electrically  conductive  parts  of  the  gen-
erator  be  property  connected  to  an  approved  earth 
ground. Local electrical codes may also require prop-
er  grounding  of  the  unit.  For  that  purpose,  a  ground-
ing  lug  is  attached  to  the  unit.  Grounding  may  be 
accomplished by attaching a stranded copper wire of 
the proper size to the generator grounding lug and to 
an  earth-driven  copper  or  brass  grounding-rod  (elec-
trode).  Consult  with  a  local  electrician  for  grounding 
requirements in your area.
the Fuel Supply
Units  with  air-cooled  engines  were  operated,  tested 
and  adjusted  at  the  factory  using  natural  gas  as  a 
fuel. These  air-cooled  engine  units  can  be  converted 
to use LP (propane) gas by making a few adjustments 
for best operation and power.
LP  (propane)  gas  is  usually  supplied  as  a  liquid  in 
pressure  tanks.  Both  the  air-cooled  and  the  liquid 
cooled  units  require  a “vapor  withdrawal”  type  of  fuel 
supply  system  when  LP  (propane)  gas  is  used. The 
vapor  withdrawal  system  utilizes  the  gaseous  fuel 
vapors that form at the top of the supply tank.
The  pressure  at  which  LP  gas  is  delivered  to  the 
generator  fuel  solenoid  valve  may  vary  considerably, 
depending on ambient temperatures. In cold weather, 
supply pressures may drop to “zero”. In warm weath-
er, extremely high gas pressures may be encountered. 
A primary regulator is required to maintain correct gas 
supply pressures.
Current recommended gaseous fuel pressure at the inlet 
side of the generator fuel solenoid valve is as follows:
lP
NG
Minimum water column
10 inches
5 inches
Maximum water column
12 inches
7 inches
A  primary  regulator  is  required  to  ensure  that  proper 
fuel supply pressures are maintained.
*
   DaNGEr: lP aND Natural Gas arE BotH 
HiGHlY EXPlosiVE. GasEous fuEl liNEs 
must BE ProPErlY PurGED aND tEstED 
for lEaKs BEforE tHis EQuiPmENt is 
PlacED iNto sErVicE aND PErioDicallY 
tHErEaftEr. ProcEDurEs usED iN 
GasEous fuEl lEaKaGE tEsts must 
comPlY strictlY WitH aPPlicaBlE fuEl 
Gas coDEs. Do Not usE flamE or aNY 
sourcE of HEat to tEst for Gas lEaKs. 
No Gas lEaKaGE is PErmittED. lP Gas is 
HEaViEr tHaN air aND tENDs to sEttlE iN 
loW arEas. Natural Gas is liGHtEr tHaN 
air aND tENDs to sEttlE iN HiGH PlacEs. 
EVEN tHE sliGHtEst sParK caN iGNitE 
tHEsE fuEls aND causE aN EXPlosioN.
Use  of  a  flexible  length  of  hose  between  the  genera-
tor fuel line connection and rigid fuel lines is required. 
This  will  help  prevent  line  breakage  that  might  be 
caused by vibration or if the generator shifts or settles. 
The  flexible  fuel  line  must  be  approved  for  use  with 
gaseous fuels. 
Flexible  fuel  line  should  be  kept  as  straight  as  possi-
ble between connections. The bend radius for flexible 
fuel line is nine (9) inches. Exceeding the bend radius 
can cause the fittings to crack.
the tranSFer SWitch / load center
A transfer switch is required by electrical code, to pre-
vent electrical feedback between the utility and stand-
by power sources, and to transfer electrical loads from 
one power supply to another safely.
TRANSFER SWITCHES:
Instructions and information on transfer switches may 
be found in Part 3 of this manual.