Generac Power Systems 20 kW LP ユーザーズマニュアル

ページ / 192
sEctioN 4.4
DiaGNostic tEsts
Page 131
PORT 3
PORT 1
PORT 2
Figure 20 (12-20 kW) Gas Pressure Test point
note: Where a primary regulator is used to estab-
lish fuel inlet pressure, adjustment of that regula-
tor is usually the responsibility of the fuel supplier 
or the fuel supply system installer.
12-20 kW UNITS ONLY:
note: the test port (port 3) below the fuel solenoid 
maybe used to take a fuel pressure reading before 
the  fuel  solenoid.  consistent  pressure  should  be 
measured  at  this  port  while  the  generator  is  run-
ning and when the generator is off.
RESULTS:
1.  If fuel supply and pressure are adequate, but engine will 
not start refer back to flow chart.
2.  If generator starts but runs rough or lacks power, repeat 
the  above  procedure  with  the  generator  running  and 
under  load. The  fuel  system  must  be  able  to  maintain 
10-12 inches water column at all load requirements for 
propane, and 5-7 inches water column for natural gas. 
If proper fuel supply and pressure is maintained, refer to 
Problem 18 Flow Chart.
teSt 67 – check circuit Board Wire 14 
output
DISCUSSION:
During  any  cranking  action,  the  circuit  board’s  crank 
relay  and  run  relay  both  energize  simultaneously. 
When the run relay energizes, it’s contacts close and 
12 VDC is delivered to Wire 14 and to a fuel solenoid. 
The solenoid energizes open to allow fuel flow to the 
engine. This  test  will  determine  if  the  circuit  board  is 
working properly.
PROCEDURE: 12-20 kW UNITS
1.  Set the AUTO-OFF-MANUAL switch to OFF.
2.  Set a VOM to measure DC voltage.
3.  Disconnect Wire 14 from the fuel solenoid (FS).
4.  Connect the positive test lead to the disconnected Wire 
14  from  Step  3.  Connect  the  negative  test  lead  to  a 
clean frame ground.
5.  Set AUTO-OFF-MANUAL switch to the MANUAL position. 
The meter should indicate battery voltage.
a.  If  battery  voltage  is  indicated,  refer  back  to 
flow chart.
b.  If  battery  voltage  is  not  measured,  navigate  to 
the Digital Output display.
c.  Press “ESC” until the display screen is present.
d.  Press the right arrow key until “Debug” is flashing. 
Press “Enter”.
e.  Press  the  right  arrow  key  until  “Outputs”  is 
flashing. Press “Enter”.
DEBUG
OUTPUTS
OUTPUT 5
OUTPUTS 1 - 8:
1   0   1   1   0   0   0   1  
Figure 21. The Home Page, Debug and Output 
Screens
f.  Output 5 is Wire 14 out from the printed circuit 
board.  If  the  printed  circuit  board  is  functioning 
properly, Output 5 will change from a “0” to a “1” 
while the unit is cranking.
g.  If  voltage  was  not  measured  in  Step  5  and 
output  did  not  change  in  Step  5f,  replace  the 
printed circuit board.
note:  disconnect  the  7.5  amp  Fuse  before  dis-
connecting the j2 connector.
h.  If voltage was not measured in Step 5 and out-
put changed in Step 5f, remove the J1 connec-
tor  from  the  printed  circuit  board.  See  Figures 
on Pages 92-95.
DC CONTROL
Part 4