 Site Requirements and Prerequisites 2-1 
Chapter 2 
Installation and Setup 
2.1 Introduction 
This chapter describes installation and setup procedures for the standalone  
RIC-155 device.  
After installing the unit: 
•  Refer to 
Chapter 3
 for the operating instructions. 
•  Refer to 
Chapter 4
 for the detailed system configuration procedures using an 
ASCII terminal connected to the RIC-155 control port. 
If a problem is encountered, refer to 
Chapter 5
 for test and diagnostic instructions. 
The RIC-155 standalone unit is designed for desktop or bench installation and is 
delivered as a fully assembled unit. No provisions are made for bolting the unit to 
a tabletop. 
 
 
Always observe standard safety precautions during installation, operation, and 
maintenance of this product. 
 
2.2 
Site Requirements and Prerequisites 
AC-powered RIC-155 units should be installed within 1.5m (5 ft) of an 
easily-accessible grounded AC outlet capable of furnishing the voltage in 
accordance with RIC-155 nominal supply voltage.  
DC-powered RIC-155 unit requires a -48 VDC or 24 VDC power source, which 
must be adequately isolated from the main supply.  
Allow at least 90 cm (36 in) of frontal clearance for operating and maintenance 
accessibility. Allow at least 10 cm (4 in) clearance at the rear of the unit for signal 
lines and interface cables.  
The ambient operating temperature of RIC-155 should be 0 to 50°C (32 to 122°F), 
at a relative of up to 90%, non-condensing.  humidity 
Warning