3.5.2  A Qualified Electrical Contractor must perform the hardwiring when 
connecting the Input and Output wires to the terminal block on the 
ED6200T UPS. Apply 22.1lb-in of torque force when connecting to the 
terminal blocks. The Input and Output of the UPS MUST be Hardwired. 
 
 
 
 
 
 
 
 
 
 
 
3.5.2.1  INPUT connections for the ED6200T Hardwired only: 
1.  Connect L1 from the utility to terminal L12. 
2.  Connect L2 from the utility to terminal N1. 
3.  Connect the earth ground from the utility to terminal G1. 
 
CAUTION - To reduce the risk of fire, connect the UPS Utility input to a branch 
circuit with an over-current protection of 40 amperes in accordance with the 
National Electric Code, ANSI/NFPA 70. Use No. 8 AWG, 60
°C copper wire and 
apply 22.1lb-in of torque force when connecting to the terminal blocks. 
 
3.5.2.1.1  OUTPUT connections for ED6200T Hardwired only: 
1.  Connect L1 from the load to terminal L22. 
2.  Connect L2 from the load to terminal N22. 
3.  Connect the earth ground from the load to terminal G2. 
 
A Qualified Electrical Contractor must perform the hardwiring. The outputs 
must be connected to an over-current protection device (circuit breaker) of 30 
amperes in accordance with the National Electric Code, ANSI/NFPA 70. Use No. 
10 AWG, 60
°C copper wire and apply 22.1lb-in of torque force when connecting 
to the terminal blocks. 
 
 
 
 
 
 
 
 
19
3.6. 
Operation and Setup Instructions 
 
3.6.1  Startup in the Normal Mode 
 
3.6.1.1  Switch the Utility power circuit breaker (at the service panel) to the On 
position. 
3.6.1.2  Switch the UPS’s Input circuit breaker (on the rear panel) to the On 
position. 
3.6.1.3  The UPS will startup. The Green LEDs 
 & 
 will illuminate to show 
the Utility and Bypass Inputs are normal. The LCD display will display 
drawing A then drawing B. 
 
 
 
 
A. 
 
 
 
 
 
 
 
B. 
 
 
 
3.6.1.4  The UPS is in Bypass mode. The UPS will automatically perform a self-
test. If there are no error codes displayed then the UPS has successfully 
passed the startup self-test and will start charging the batteries. 
3.6.1.5  Press and hold the On Switch (on the front panel) 
 for approximately 
3-seconds, then release. The audible alarm will sound 2-beeps then the 
LCD display will change from drawing B to drawing C.