Page 6-31
Procedure for Installing/Replacing the Inter-Cabinet Cable 
6
Procedure for Installing/Replacing the
Inter-Cabinet Cable
The Inter-Cabinet Cables (ICCs) are physically located on the back of the 
cabinet behind the panels and between the A control cabinet and the B control 
cabinet. The panels must first be opened to see the ICCs.
!
WARNING:
Damage can be done to the Inter-Cabinet Cables during removal or 
installation. Follow the guidelines listed below to minimize the possibility of 
damage to the cables and later need of replacement.
To remove ICC-A, ICC-B, or ICC-C:
1. Remove power from the system. Refer to the 
 section in 
.
2. Grasp the cable connector, not the cable itself. Attempting to remove a 
cable by pulling on the cable itself can damage the cable-to-connector 
interface.
3. Pull the cable straight out. Pulling the connector from the backplane at an 
angle can bend the backplane pins.
4. Push the ICC connector onto the insulated sleeves.
!
CAUTION:
The pins should not show through the back of this connector. If they 
do, they ICC may be shorted out.
The only way to check the connector-cable-connector integrity is with a 
continuity test.
To re-install ICC-A, ICC-B, or ICC-C:
1. Verify that the backplane pins are not bent. If any are bent, they must be 
straightened or replaced before continuing.
2. Align the ICC connector with the backplane pins and push partially into 
place.
3. Use a dental mirror and light to view the back sides of the connector. 
Determine that all 50 backplane pins are seated correctly in the ICC 
connector.
4. Push the ICC connectors fully onto the insulated sleeves. The pins should 
not show through the back of the connectors. If the pins show through, the 
ICC may be shorted out.