Page 10-1564
XXX-BD (Common Port Circuit Pack) 
10
Neon Test (#220)
This test checks the voltage required to light the neon lamp on an analog 
terminal. A relay connects a 150V DC source from the backplane of the circuit 
pack onto the voltage bus, and another relay connects a 2K shunt from the bus 
to ground. Current in the line is then monitored to determine if the voltage is 
present.
The neon test runs only for TN746 and TN769 Analog circuit packs. If the circuit 
pack is not a TN746 or TN769, the test returns PASS, but there is no testing done 
to the circuit pack.
Table 10-530.
TEST #220 Neon Test 
Error 
Code
Test 
Result
Description/ Recommendation
1004
ABORT
The port was seized by a valid call during the test. The test has been 
aborted. Use the 
display port PCSSpp
 command to determine the station 
extension. Use the 
status station
 command to determine the service state 
of the port. If the service state indicates that the port is in use, then the port 
is unavailable for certain tests. (Refer to the "Status Commands" section in 
 for a full 
description of all possible states.) You must wait until the port is idle before 
retesting.
1. Retry the command at one-minute intervals a maximum of five times.
2. If the test continues to abort, escalate the problem.
1008
ABORT
Could not allocate a ringing circuit. Either all the ringing circuits are in use, 
or the ringing generator is defective or is not wired correctly.
1. Retry the command at one-minute intervals a maximum of five times.
2. If the test continues to abort, look for RING-GEN errors in the Error 
Log. If an ABORT 1008 occurs for this test on other circuit packs as 
well, then the ringing generator may be defective or is not wired 
correctly (see errors for RING-GEN). If it doesn’t occur on port test 48 
for ANL-16-L, then all four ring phases are in use.
3. If the test to continues to abort, escalate the problem.
Continued on next page