DWBS Installation Checklist
A-2
Issue 5   June 1999
Checklist
The following table is a checklist of tasks for completing a DWBS installation. 
Where appropriate, references to the corresponding pages for a description of the 
tasks indicated are also provided. Unless otherwise indicated, the page 
references are for the DWBS Installation document.
Table A-1.
Checklist of Tasks and Corresponding Description Page References for 
Completing a DWBS Installation
Task: Have you...
Page Yes/No
Wired the CAUs according to the SDSC installation 
plan?
3-30 
Oriented the CAUs (azimuth and tilt) according to the 
SDSC installation plan using brackets when required? 
3-49 
Wired the WFBs according to the SDSC installation 
plan?
3-20 
Installed and wired the power supplies for each WFB 
that has an attached CAU?
3-21 
Verified that the DC power leads for WFB are 
“doubled up?” 
3-13
Placed the TN789 circuit packs into the appropriate 
slots?
3-11 
Terminated WFBs 1A and 1B to ports 1 and 2 of the 
first TN789 circuit pack? 
3-10 
Terminated WFBs 2A and 2B to ports 1 and 2 of the 
second TN789 circuit pack?
3-10 
Terminated all remaining WFBs properly?
3-10
Installed the WT download cable?
4-7 
Upgraded the switch software to V5 or greater?
2-1 
Enabled wireless capabilities via the Optional 
Features form by entering the change 
system-parameters customer-options
 command? 
(Remember to log off and log on again.) 
2-2 
Enabled wireless capabilities via the 
Wireless-Related System-Parameters form by 
entering the change system-parameters wireless 
command? 
2-3 
Administered the Carrier-Frequencies form?
2-7