Piping
17
Figure 15 Hard pipe connection diagram
6.6.1 Leak-Checking and Evacuation
Refer to the Liebert XDC or Liebert XDP user manual for procedures for evacuation, leak check, 
charging and startup.
6.6.2 Header System
The Liebert XDR module system with optional flexible piping requires use of the Liebert XD prefabri-
cated piping assembly. The prefabricated piping is compatible with the Liebert XD Flex Pipe required 
to attach to the Liebert XDR modules. For the details on piping connection locations, see Figure 14.
For additional information, refer to the Liebert X-treme Density System Design Manual, SL-16655, 
available at the Liebert Web site: 
Top of 
Liebert XDR 
and 
Equipment 
Rack
Return Main
(seen from end )
2-1/8" O.D.
or 2-5/8" O.D.
Recommended Arc
Acceptable 
Arc
Copper Tubing
Total length of each line 
from Liebert XDR to 
Main not to exceed 72"  
(1829 mm)
7/8” Refrigerant -Grade
Full-Port Ball Valve
Field-Supplied and
Field-Installed
Return from
Cooling Module
Supply Main
(seen from end )
1-1/8" O.D.
or 1-3/8" O.D.
1/2” Refrigerant -Grade
Full-Port Ball Valve
Field-Supplied and 
Field- Installed
Supply 
to Cooling
Module
Rear of 
Equipment Rack
Refer to Table 1 for details.