Champion eucc series ユーザーガイド

ページ / 241
194
Utilities _____________________
 
Plumbing, Steam, Condensate, Drain
Basic Service • Utilities
Refer to the utility summary below before you begin troubleshooting a condition.
Shut-off valves
1.
Installed in all supply lines to allow for servicing of the machine.
Pressure Regulating Valves
1.
Installed in the incoming water supply lines.
2
Installed in the incoming steam supply lines as close to the machine as possible.
Water Hammer Arrestor
1.
ASSE-1010 standard or equivalent, should be installed in the common water
supply line at the service connection.
Hot Water Supply
1.
3/4" NPT 140°F.  Flow pressure 20-22 PSI,  for built-in 40°F rise steam/electric booster
2.
3/4" NPT 110°F. Flow pressure 20-22 PSI, for built-in 70°F rise steam/electric booster
3.
3/4" NPT 180°F. Flow pressure 20-22 PSI, without built-in booster
Cold Water
1.
1/2" NPT 65°F tempering cold water connection, for prewash with cold water thermostat.
Steam Supply
1.
Refer to the P&E Connections Drawing or consult the factory.
Steam Condensate
1.
1/2" NPT with no back pressure.
Drain
1.
1-1/2" NPT for main drain line.
2.
3/4" NPT for booster relief valve to an open drain.
IMPORTANT !
The steam condensate line 
CANNOT BE HIGHER
  than the lowest steam trap.
A condensate pump, (by others) , must be installed
 in the condensate line if
the installation requires the line to be higher than the lowest steam trap.