Netgear M7300-24XF (XSM7224S) - ProSAFE 24-port, 10 Gigabit Stackable L2+ Managed Switch ソフトウェアガイド
Getting Started
8
7000 Series Managed Switch
To connect a terminal to the switch console port using out-of-band connectivity:
1.
Connect an RS-232 crossover cable to the terminal running VT100 terminal emulation
software.
software.
2.
Configure the terminal emulation software as follows:
a. Select the appropriate serial port (serial port 1 or serial port 2) to connect to the
console.
b. Set the data rate to 9600 baud.
c. Set the data format to 8 data bits, 1 stop bit, and no parity.
d. Set the flow control to none.
e. Select the correct mode under Properties.
f. Select Terminal keys.
Note:
When using HyperTerminal with Microsoft Windows 2000, make
sure that you have Windows 2000 Service Pack 2 or later installed.
With Windows 2000 Service Pack 2, the arrow keys function
properly in HyperTerminal’s VT100 emulation. Go to
With Windows 2000 Service Pack 2, the arrow keys function
properly in HyperTerminal’s VT100 emulation. Go to
service packs.
3.
Connect the female connector of the RS-232 crossover cable directly to the switch console
port, and tighten the captive retaining screws.
port, and tighten the captive retaining screws.
Starting the Switch
1.
Make sure that the switch console port is connected to a VT100 terminal or VT100
terminal emulator through the RS-232 crossover cable.
terminal emulator through the RS-232 crossover cable.
2.
Locate an AC power receptacle.
3.
Deactivate the AC power receptacle.
4.
Connect the switch to the AC receptacle.
5.
Activate the AC power receptacle.
When the power is turned on with the local terminal already connected, the switch goes
through a power-on self-test (POST). POST runs every time the switch is initialized and
checks hardware components to determine if the switch is fully operational before completely
booting. If POST detects a critical problem, the startup procedure stops. If POST passes
successfully, a valid executable image is loaded into RAM. POST messages display on the
terminal and indicate test success or failure. The boot process runs for approximately 60
seconds.
through a power-on self-test (POST). POST runs every time the switch is initialized and
checks hardware components to determine if the switch is fully operational before completely
booting. If POST detects a critical problem, the startup procedure stops. If POST passes
successfully, a valid executable image is loaded into RAM. POST messages display on the
terminal and indicate test success or failure. The boot process runs for approximately 60
seconds.