AEG PROTECT 1.11 ユーザーズマニュアル

ページ / 61
56
11.
When  the  displays  are  lit  as  described,  switch  on
your  loads  one  after  the  other.  When  doing  this, 
take  care  not  to  exceed  the  maximum  permitted 
load  capacity  of  the  UPS  systems.  Also  take  into 
account 
the 
reserve 
capacities 
if 
active 
redundancy should be required.
9.3.2
Changes to the parallel system
If  you  would  like  to  add  a  UPS  to  the  parallel  system  or 
remove  a  UPS  from  the  parallel  system,  this  step  is  always 
done  by  returning  the  UPS  systems  to  BYPASS  operating 
mode.
i
Load supply through mains operation! 
(No UPS protection during this measure).
First, switch off the inverters of the UPS systems one after the 
other  (actuate  the  “OFF”  pushbuttons).  All  UPS  systems 
function  in  SBS/bypass  operation.  Check  the  operating  state 
on  the  operating  panels.  Next,  active  the  integrated  manual 
bypasses  (no. 3,  p.  26/27)  on  the  back  of  each  UPS.  To  do 
this, first remove the 4 screws of the covers on the back.
Put  the  mains  input  miniature  circuit  breakers  of  each  UPS 
(no. 2,  p.  26/27)  to  “OFF”  position.  Use  your  central  external 
manual  bypass  to  bypass  the  loads,  i.e.  activate  the  bypass 
operation and remove the load supply from the UPS busbar.
The  voltage  of  each  UPS  is  disconnected  in  its  low-voltage 
main distribution. You can now expand or reduce your parallel 
system.  Pay  attention  to  the  jumpers  “JP1”  /  “JP2”  and  the 
parallel  operation  cables.  The  subsequent  start-up  is  carried 
out as described in chapter 9.3.1.
i
If  you  only  want  to  switch  off  a  UPS  in  the 
parallel  system,  press  the  “OFF”  pushbutton 
twice  in  succession  to  do  this.  In  this  way, 
individual  UPS  systems  can  be  disconnected 
from the parallel operation busbar.