Installation Preparation 
 
Prior to installation, the location of all LanPaks needs to be determined.  A detailed map of the 
areas to be covered will be required.  These should be in .dwg or .dwx format and provided to 
Radianse as early as possible.  This map will be the basis for determining the positions of the 
LanPaks throughout your facility.  With the initial positions determined a final walkthrough to 
determine exact locations will be required.  At this time, any physical issues that will impact the 
ability to install (ex. light fixtures, cabinets, etc) will be taken into account and final positioning 
will be verified.  A Radianse team member will work with you to complete this task.   
 
In addition to the LanPak installation you should prepare the necessary information for the 
LightPak installation.  A detailed list of any resources that will be tracked should be obtained.  
This could include a staff roster and/or equipment inventory. 
 
LanPak Installation 
 
Members of the Radianse team will install the LanPaks.  Prior to installation, you should ensure 
that all network ports have been installed, activated and tested.  For installations using power 
over UTP, this includes the installation and testing of the power injectors.  For installations not 
using power over UTP, the installation and location of electrical outlets should be verified. 
 
A Radianse team member will be on-site for the installation of the LanPaks.  As a result, detailed 
installation and configuration instructions are not included.  Should a LanPak require 
replacement, any replacement equipment will be shipped to you pre-configured and ready to be 
plugged into your network.   
 
Should you need to remove an installed LanPak, slide the LanPak upward and then away from 
the wall to remove it from the bracket.  Unplug the power cord (if one exists) from the back of 
the LanPak (Note: most LanPaks will not have a separate power cord) and then unplug the 
network cable from the LanPak.   
 
With the old LanPak removed, you can now install the new LanPak.  Plug the network cable and 
the power cable (if one exists) back into the LanPak.  Place the new LanPak on the bracket, 
lining up the mounting holes, and slide the LanPak downward to lock it into place.  Plug the 
network cable back into the data port.  Once installed, any extra cable can be tucked behind the 
LanPak. 
   
LightPak 
 
LightPaks come preconfigured and ready for use.  There is no hardware setup required.