Nokia Solutions and Networks T5BR1 ユーザーズマニュアル

ページ / 162
Prepare to Leave the Site 
– continued
08/01/2001
5-5
1X SC
t
4812ET Lite BTS Optimization/ATP
PRELIMINARY
Table 5-6: Remove LMF
Step
Action
6
Disconnect the CDMA LMF terminal Ethernet port from the BTS frame.
7
Disconnect the CDMA LMF terminal serial port, the RS–232–to–GPIB interface box, and the
GPIB cables as required for equipment transport.
 
Connecting BTS T1/E1 Spans
Before leaving the site, connect any T1 or E1 span connectors removed
previously to allow the LMF to control the BTS. Refer to Table 5-7 and
Figure 3-7.
Table 5-7: Connect T1 or E1 Spans
Step
Action
1
Re–connect any disconnected span connectors to the Span I/O A and B boards.
2
If equipped, ensure the CSU is powered on.
3
Verify span status, ensuring the OMC–R/CBSC can communicate with the BTS.
Before Leaving the site
Be sure all requirements listed in Table 5-8 are completed before leaving
the site.
Table 5-8: Check Before Leaving the Site
Step
Action
1
All battery circuit breakers (for occupied shelves) are  ON (pushed in).
2
Both heat exchanger circuit breakers on the DC PDA are set to  ON (pushed in), and the heat
exchanger blowers are running.
3
The External Blower Assembly (EBA) power cable is connected, and the EBA is running.
4
The MAP power switch is set to  ON, and the POWER (green) LED is lighted.
5
The BATT TEST switch on the MAP is set to  OFF, and the BATT. TEST (amber) LED is not lighted.
6
No alarm conditions are being reported to the CBSC with all frame doors closed.
5