Repeat this for procedure for each bolt, then tighten all the nuts so that the scanner is secure. 
 
 
NOTE: Use the bolts supplied as these are hardened stainless steel and the correct length.   
 
3.3.8 
When to install the open array 
IMPORTANT:  Install the open array onto the scanner AFTER you have connected the interconnection 
cable to the scanner otherwise you'll have to remove the open array from the scanner, and then re-
install it. 
 
 
3.3.9 
Install the radar processor 
Install the radar processor in a dry location away from spray, rain, drips, and condensation.   
The location site must allow you to easily connect the radar processor to the ship's ground, the 
interconnection cable, the power cable, and the 6000i and 6100i radar communications cable or the 
8000i network cable.  Check that these cables and the ship's ground can easily reach the radar 
processor BEFORE you drill. 
The radar processor dimensions are shown on the drilling template. Follow the instructions on the 
drilling template to install the radar processor. 
 