Figure 1 
Wiring 2 units (adjustable voltage on unit #1)
 
Operation:  
1.  Plug power supply into octal socket. 
2.  Turn on power source. 
3.  Voltage adjustments are made by removing plug 
button on top of power supply case. This will 
expose a screwdriver slotted adjustment. Turn the 
adjustment clockwise to increase voltage, or 
counterclockwise to decrease voltage. When wired 
as described above, the adjusted voltage will be 
applied across unit #1.  
4.  With switch in position P1, unit #1 is energized with 
adjusted voltage and unit #2 is de-energized.  
5.  With switch in position P2 (normally closed), unit 
#2 is energized with 100 VDC and unit #1 is de-
energized.  
6.  If unit fails to operate, refer to the Troubleshooting 
section.  
Note: If unit #1 is energized with fixed 100 VDC, and 
unit #2 with adjustable DC voltage, remove lead 
between terminal 2 of octal socket and P2
of switch. 
Add lead between terminal 2 of octal socket and P1
of 
switch.
 
Model 250 used with 2 units – adjustable voltage 
on both units.Connection Instructions (See Figure 
2):
 
1. All connections are made to terminals on octal 
socket.  
2.  Connect unit #1 to terminals 6 and 8.  
3.  Connect unit #2 to terminals 3 and 6.  
4.  Connect a SPDT switch to terminals 3, 7, and 8; 
the switch common must be connected to terminal 
7. A maintained-contact type SPDT switch should 
be used.  
5.  Connect 115 VAC, 50-60 Hz to terminals 1 and 5. 
Warning:  The neutral or grounded side must be 
connected to terminal 5.  
 
Figure 2 
Wiring 2 units (adjustable voltage on both units)
 
Operation:  
1.  Plug power supply into octal socket.  
2.  Turn on power source.  
3.  Voltage adjustments are made by removing plug 
button on top of power supply case. This will 
expose a screwdriver slotted adjustment. Turn the 
adjustment clockwise to increase voltage, or 
counterclockwise to decrease voltage. When wired 
as described above, this same adjusted voltage 
will be applied across both unit #1 and unit #2.  
4.  With switch in position P1, unit #1 is energized with 
adjusted voltage and unit #2 is de-energized.  
5.  With switch in position P2 (normally closed), unit 
#2 is energized with adjusted voltage and unit #1 is 
de-ener-gized.  
6.  If unit fails to operate, refer to the Troubleshooting 
section. 
Model 250 used with 1 unit. Connection 
Instructions (See Figure 3): 
 
1. All connections are made to terminals on octal 
socket.  
2.  Connect unit (clutch or brake) to terminals 6 and 8.  
3. Connect switch to terminals 7 and 8; the switch 
common should be connected to terminal 7. Use a 
maintained contact SPDT (shown in Figure 3) or 
SPST switch.  
4.  Connect 115 VAC, 50-60 Hz to terminals 1 and 5. 
Warning:  The neutral or grounded side must be 
connected to terminal 5.