 HYDRONIC PIPING
Consider near boiler piping as part of the boiler for proper 
water level control and to produce dry steam. 
Correct near boiler piping is crucial to proper operation of 
boiler and heating system.
Follow these recommendations carefully.
1. 
Place boiler in selected location as near chimney as 
possible. 
2. 
Install safety valve. Figure 5 and Warning on Page 8.
• Install union, if used, close to safety valve outlet.
• Install elbows close to safety valve outlet and 
downstream of union (if used).
3. 
Boiler is equipped with two 2" supply connections and 
two 2" return connections, one each on both left and 
right sides of boiler. Plug unused connections with 
furnished 2" plug and 2 x ¾ " bushing for drain valve.
4. 
When using both supply tappings to pipe system as 
shown in Figure 6b , Page 10.
• Fit headers with header offsets, swing joints, or equip 
with expansion joints, so thermal expansion and 
contraction of header does not damage boiler. Do not 
weld headers.
• Place system takeoffs from header between equalizer 
and riser to header nearest equalizer. System takeoffs 
must never be between two risers. If steam main goes 
in two directions, place two takeoffs from header, one 
for each main.
5. 
Recommended near boiler piping for gravity return 
systems is shown in Figure 8 page 11. For gravity return 
systems, bottom of lowest steam carrying pipe, dry 
return or end of steam main, must be at least 28” above 
normal water level line on left side of boiler. 
6. 
Equip all boilers in gravity return systems with Hartford 
Loop as shown in Figure 6a and 6b page 10.
7. 
Piping vertical risers from boiler to header, risers must 
be minimum of 24" high above water line.
8. 
Steam riser(s) and header shall be 2" pipe. 
9. 
Equalizer line shall be minimum 1-1/2" pipe size.
10. 
Near boiler piping shall include 2" tee with female 
adapter and cap located on supply line as shown for 
skimming (i.e. surface blow-down).
11. 
For pumped return systems, follow condensate pump 
or boiler feed pump manufacturer’s instructions for 
proper installation and hookup. See Table 4 and Figure 
7 page 11.
12. 
Connecting cold water supply to water inlet valve, 
verify clean water supply is available. When water 
supply is from well or pump, install sand strainer at 
pump.
Table 4 - Steam Flow Rates (Gross)
Sections
Flow Rates LBS/HR
3
63.4 LBS/HR
4
94.7 LBS/HR
5
126.8 LBS/HR
6
158.1 LBS/HR
7
190.2 LBS/HR
8
221.5 LBS/HR
9
252.8 LBS/HR