Completing the Installation 
When the switch has been installed as specified above, then the unit 
can be configured as detailed below: - 
 
1.  Apply AC power to the switch. The green Power LED on the front 
panel should light. 
2. Connect the Cat. 5/5e twisted pair cables from the network 
partner devices to the RJ-45 ports on the front panel of the switch. 
When a connection is obtained, the green LK/ACT LED 
associated with the port will light. 
3.  If the fibre uplink is used, then connect the fibre link to the partner 
device (media converter, fibre NIC card or fibre switch etc). Verify 
that the green Link LED on the fibre module is lit which indicates 
that the optical link is valid. 
4.  If advanced modes such as port-based VLANs are needed, then 
use the console port to configure the switch.  
5. If legacy devices that do not support auto-negotiation are 
connected to the RJ45 ports then it may be necessary to 
configure the switch to match the speed and duplex modes of the 
partner devices.  
6.  Note that auto-negotiation can take up to 30 seconds to complete 
depending on the partner device. 
 
 Product Number 0-1591093-x 0-1591047-x                                                                                 Issue 1 