Switch 
The inverter is set ready for operation using the DOU switch on the 
front panel. The monitoring functions with their respective messages 
are only active when the inverter is switched on. After switch-off, all 
faults are acknowledged. The settings of the DIL switches are only 
accepted if the unit is switched off! 
3.8 
CAN Bus Interfaces X6 / X7 
The unit can be controlled and monitored using the 10-pin CAN bus 
connector X6 if the INV is installed in a power supply cabinet with 
PSM control unit. 
The CAN bus connector X7 has no significance if one inverter in  
single operation operated without SBS. Both ends of the bus have to 
be connected to a terminating resistor when several INVs are 
operated in parallel! 
For operation with SBS, only the end of the bus on the INV must have 
a terminating resistor connected; a bus terminating resistor is 
integrated in the SBS! (See Figure 1.) 
3.9 DIL 
Switch 
An 8-pin DIL switch is arranged below the LCD. All settings of / 
changes to the DIL switch are only activated after the INV has been 
switched off using the ON/OFF switch. It is counted from the left S2.1 
to the right S2.8, switches that are pushed in at the bottom signify 
"open"! The setting of the switches is shown on the display as a 
check whenever a change is made; 0 = open; 1 = closed. 
Switches S2.1, S2.2 and S2.3: Number of parallel INVs in the 
system 
The settings must be the same on all INVs and the SBS! 
Standard setting: 
1 INV: S2.1, S2.2 and S2.3 open 
 
 
S2.1 S2.2 S2.3 
1 INV 
0 0 0 
2 INVs 
0 0 1 
3 INVs 
0 1 0 
4 INVs 
0 1 1 
5 INVs 
1 0 0 
6 INVs 
1 0 1 
7 INVs 
1 1 0 
8 INVs 