Sterling A0554831 ユーザーズマニュアル

ページ / 70
2-40 HP Portable Chillers 
Chapter 3: Installation 
25 of 70 
3-9 Water 
Reservoir 
All portable chillers shipped during the fall, winter, or spring, or those units that are shipped 
from stock are flushed at the factory with a water/ethylene glycol solution to prevent piping 
components prone to retaining water from freezing. During startup and when additional 
solution is required, refer to the ethylene glycol and propylene glycol curves in Figure 6 on 
page 26. Add a pre-mixed solution of industrial quality (not automotive) ethylene glycol or 
propylene glycol and water to provide freeze protection to a temperature 20ºF (11ºC) below 
the normal chiller operating temperature set point.  
Glycol and/or water, with an inhibitor, should be used to protect the materials (copper, steel, 
stainless steel, and bronze) in the system from corrosion. If you intend to use straight water, 
we strongly advise a minimum leaving water temperature of 50ºF (10ºC) or contact the 
service department. 
The following glycol products are available: 
Part Number 
Description 
A0541358 
Ethylene glycol, 5 gallons (18.9 liters) 
A0539637 Ethylene 
glycol, 
55 gallons (208.2 liters) 
A0542990 Propylene 
glycol, 
5 gallons (18.9 liters) 
A0542991 Propylene 
glycol, 
55 gallons (208.2 liters) 
 
Caution!  Do not connect make-up water directly to the chilled water reservoir unless you 
have an approved automatic water make-up system installed. 
Note: 
The reservoir is not designed to withstand water pressure. The fill opening and 
vent line must be vented to the atmosphere for proper operation. The optional 
automatic make-up system is described in section 3-10 on page 27.
 
Caution!  Do not pressurize tank. Fill and vent lines must be open to atmosphere. Supply 
and return connections must be trapped and vented to allow vertical risers to 
drain into tank. Do not overfill system. Allow enough free space in tank for 
vertical piping to drain. 
If your application has chilled water or process piping above the reservoir fill and vent level, 
trap and vent the supply and return lines to allow vertical piping to drain into tank.  
Note: 
In applications where the process or process piping is above the reservoir, take 
steps to prevent over pressurization of the reservoir. This condition can occur 
on system shutdown when the water in the system drains into the reservoir. To 
prevent this, a vacuum breaker should be installed at the high point of the “To 