Installing a Vent Near a Window Ledge, 
Other Type of Projection or on Siding (vinyl, aluminum, etc.)
Direct  vent  furnaces  are  designed  to  be  installed  on  a  uniform 
outside wall. When the wind comes from any angle (up, down or 
from either side), it must hit the vent cap equally over both the air 
inlet and the flue outlet portions of the vent. Any wall projection, 
such as a door or window casing, which disturbs the wind on one 
side of the air inlet section will result in back pressure on the flue 
section smothering the flame and eventual pilot outage.
When the vent cap is to be installed on siding or it appears that a 
projection within 6” of any side of the air inlet section could shield 
the air inlet section, the entire vent should be supported away from 
the wall at least the distance of the projection. 2” x 4”  framing 
whose outside dimensions match the overall dimensions of the 
mounting  plate  is  recommended. The  2”  x  4”  framing  protects 
siding from possible warpage or discoloration. All joints can then 
be sealed and painted. The wall depth plus the additional depth 
of the 2” x 4” framing should not exceed a total depth of 14” for 
DVC-35T. (See Figure 10) 
Vinyl siding vent kit, DV-822, is available from Empire Comfort 
Systems, Inc. The depth is 3”, which enables the vent cap to be 
extended away from siding or projections. The wall depth plus the 
additional 3” depth of the vinyl siding vent cap extension should 
not exceed a total depth of 19” for DVC-35T. (See Figure 11)
Warning: When vinyl siding vent kit, DV-822 or 2” x 4”  
framing  is  added  to  an  existing  installation  (furnace  is 
installed) do not attempt to add sections of pipe to the flue 
outlet tube or air inlet tube. An air tight seal is required for 
both tubes. Refer to Parts List, page 16 to order tubes.
Figure 10 
Figure 11
Installing Vent Assembly
Attention: DO NOT attempt to cut vent tubes. When you order 
appropriate vent kit for measured wall depth the vent tubes will 
fit together.
1.  Place  provided  caulking  beneath  the  collar  of  the  outside 
mounting plate. Use additional caulking to correct uneven wall 
surface, such as clapboard.
2.  Insert six inch air tube on outside mounting plate INTO six 
inch  air  tube  attached  to  air  drop.  Place  four  inch  flue  tube 
on vent cap OVER four inch flue tube attached to outlet box. 
Position the outside mounting plate so that six inch air tube 
has a slight downward slope to the outside. The downward 
slope is necessary to prevent the entry of rainwater. Attach 
outside mounting plate to exterior wall with four (4) 10 x 1 1/2” 
screws.
3.  Installation is completed.
Reassembly And Resealing Vent-Air Intake System
When vent-air intake system is removed for servicing the furnace, 
the following steps will assure proper reassembly and resealing of 
the vent-air intake assembly.
1.  Remove old caulking beneath the collar of the outside mounting 
plate. Apply  new  caulking  beneath  the  collar  of  the  outside 
mounting plate. Use additional caulking to correct uneven wall 
surface, such as clapboard.
2.  Insert six inch air tube on outside mounting plate INTO six 
inch air tube attached to air drop. Position the outside mounting 
plate so that six inch air tube has a slight downward slope to 
the outside. The downward slope is necessary to prevent the 
entry of rainwater. Attach outside mounting plate to exterior 
wall with four (4) 10 x 1 1/2” screws.
3.  Place four inch flue tube on vent cap OVER four inch flue tube 
attached to outlet box. Attach vent cap to outside mounting plate 
with three (3) 10 x 1/2” screws. 
4.  Reassembly  and  resealing  vent-air  intake  system  is 
completed.