14.8 Completion
For the Republic of Ireland it is necessary to complete a
“Declaration of Conformity” to indicate compliance to I.S.813.  An
example of this is given in the current edition of I.S.813. In
addition it is necessary to complete the
Commissioning Checklist in Section 24 of this manual (Page 60).
14.7 External sensor and ambient sensor set-up (where fitted)
1. The system must be visually checked for soundness;
2. Fill the condensate trap with water, by pouring 
1
/
2
litre of water into the exhaust flue connector (see 
Fig. 39).  N.B. In the event of a prolonged period of 
system shutdown, the condensate trap should be 
filled before any renewed use.  A shortage of water 
in the trap could possibly lead to a temporary 
leakage of fumes into the air, until it refills itself;
3.  Ensure that the flue is fitted correctly;
4.  Allow the central heating system to warm up and adjust 
the central heating temperature control knob 31 (Fig.1), 
check the burner modulates between the high and low 
settings;
5.  Range rate the thermal power for central heating as 
detailed in Section 14.5. To adjust the maximum heating
power it is necessary to follow the steps in Section 14.5 
Menu 4. and adjust in relation to the chart on Page 35
(Fig. 42);
6. Check the gas rate;
7. Record the finding in the Benchmark Commissioning 
Checklist (Page 59);
8.  Run the domestic hot water and adjust to the correct 
water flow rate, adjust the domestic hot water 
temperature control knob 30 (Fig.1) to ensure the burner
modulates between the high and low settings;
9.  Balance the central heating system until all return 
temperatures are correct and equal;
10. Turn the boiler off by pressing the On/Off button 27
(Fig.1) to OFF, disconnect the gas pressure gauge, 
retighten the screw and relight the boiler;
11. Re-examine the central heating, domestic hot water and 
old water supplies for soundness;
12. If external controls have been disconnected, reconnect
and test;
13. Refit the boiler casing.
14.9 Operational checks