  Before you begin your installation, please read the following:
Drop-in Installation
• 
Observe all local and building codes.
• 
Determine which tools will be used during the installation.
• 
Additional bathtub drain parts and plumbing are commercially available at plumbing and hardware stores.
• 
Drain/Overflow rough-in information is included with your bathtub in the installation instruction manual.
Flashing
Exploded View
1˝ x 4˝ 
(25mm x 101mm)
Not For Support
Mortar or 
Adhesive
Subfloor 
Sealant
Tile
Complete the bathtub surround installation.
1
  Install drain/overflow according to the 
manufacturer’s instructions. Refer also to the 
Technical Specifications Manual.
  Watertight installation of the drain is the installer’s 
responsibility. Drain leakage is excluded from the 
Jacuzzi Luxury Bath warranty of this product.
2
  Install the faucet at this time. It is recommended 
that the faucet be installed by a qualified plumber.
  Proper installation of the spout plumbing and 
compliance with local codes are the responsibility of 
the installer. Jacuzzi Luxury Bath does not warrant 
connections of water supply fittings and piping, 
fill systems, or drain/overflow systems. Nor is it 
responsible for damage to the bathtub which may 
occur during installation.
  A non-flammable protective barrier must be placed 
between the soldering work and the bathtub unit to 
prevent damage to the bathtub.
3
  Prepare the cut-out hole for the bathtub using 
either the provided full scale template or the cutout 
dimensions listed in the specifications table in the 
Technical Specifications Manual.
  The template may show guides for more than one 
bathtub, be certain to select the appropriate guide 
lines. If under mounting is an option, be careful to 
select the guide lines that apply to the installation 
that you are performing.
4
  Complete all deck finish work and cover to protect 
from damaging while placing the bathtub.
5
  Insulation may be placed within the bathtub 
surround.
  Provide adequate ventilation around the motor/
pump to ensure sufficient airflow and cooling.
6
  Turn off power supply to dedicated GFCI protected 
circuits.
7
  Place a piece of scrap lumber on each of the ends 
of the cutout – this will be used as a temporary 
support prior to lowering the bathtub fully into the 
opening. 
Tile or Finished 
Surface
Substrate
Scrap Lumber
Support  
Member
Level Subfloor
Scrap Lumber
Minimum 3˝ 
(76mm) 
Clearance
Figure 8
Figure 9