GENERATOR CONTROL AND 
OPERATION
Refer to the appropriate control panel operator’s 
manual for this unit.
OPERATING UNIT WITH MANUAL 
TRANSFER SWITCH
If the generator was installed in conjunction with a 
transfer switch capable of manual operation only, the 
following procedure applies. A manually operated 
transfer switch is one that will not provide automatic 
start-up and does not include an intelligence circuit.
ENGINE START-UP AND TRANSFER
For additional information, refer to the applicable 
control panel manual for this unit, as well as any lit-
erature pertaining to the specific transfer switch.
DANGER
  The Maintenance Disconnect Switch and the 
AUTO/OFF/MANUAL switches (if so equipped) 
must be set properly, or the generator will crank 
and start as soon as the utility power to the 
transfer switch is turned off. Refer to applicable 
control panel and transfer switch manuals for 
more information.
  Do not proceed until certain that utility source 
voltage is available to the transfer switch and 
the transfer switch main contacts are set to 
UTILITY.
  Do not attempt manual operation until all power 
supplies to the transfer switch have been posi-
tively turned off, or extremely dangerous - pos-
sibly lethal - electrical shock will result.
  Transfer switch enclosure doors should be kept 
closed and locked. Only authorized personnel 
should be allowed access to the transfer switch 
interior. Extremely high and dangerous voltages 
are present in the transfer switch.
In order to transfer load from the utility source to the 
generator, follow these directions:
• Turn OFF or disconnect the utility power circuit 
to the transfer switch, using the means provided 
(such as the utility source main line circuit break-
er).
• Set the transfer handle to its UTILITY (NORMAL) 
position with load circuits connected to the utility 
power supply.
•  Set the standby generator’s main line circuit break-
er to its OFF (or OPEN) position.
• Start the generator.
‹