Close inspection: defines an inspection which encompasses those aspects covered by a visual 
inspection and, in addition, identifies those defects, such as loose bolts, which will be apparent only be 
the use of access equipment, for example steps, where necessary, and tools. 
Detailed inspection: defines an inspection which encompasses those aspects covered by a close 
inspection and, in addition, identifies those defects, such as loose terminations, which will only be 
apparent by opening the enclosure, and/or using, where necessary, tools and test equipment.  
 
a. 
Maintenance  works  are  to  be  carried  out  by  qualified  personnel  only,  i.e.  personnel  qualified 
according to TRBS 1203 or similar. 
b. 
Only such auxiliary components may be  used  in potentially  explosive atmospheres which meet 
all requirements of European and national directives and legislation.  
c. 
Components may only be replaced by original spare parts which are also approved for the use in 
Ex-atmospheres. 
d. 
Inside the Ex-atmosphere the equipment has to be serviced and cleaned regularly. The intervals 
are to be defined by the operator in compliance with the environmental rules valid at the place 
of operation. 
e. 
After  maintenance  and  repair  works  have  been  performed,  all  barriers  and  notes  removed  for 
that purpose have to be put back in their original place. 
f. 
In case  faults  of  the  equipment  are  noticed,  remove  the  equipment.  The  inner  parts  cannot  be 
maintained by the customer. Instead, send the equipment to the manufacturer for inspection. 
 
 
Activity 
Visual 
inspection 
monthly 
Close inspection 
every 6 months 
Detailed inspection  
every 12 months 
Visual  inspection  of  lining  device  for 
intactness, removal of dust settlements 
 
1
 
 
Check of entire system 
Operator’s responsibility 
 
 
9.8  Disposal 
Packaging material and worn components shall be disposed of according to the regulations applicable 
in the country of installation. 
 
                                                 
1
 
 Can be shortened or extended taking local conditions into account.