Appendix C: Calculating DCM Phase-Shifting
R
-- DISCONTINUED PRODUCT --
Perform a complete sweep of phase-shift settings during your initial system test. Use only 
positive (0 to 255) phase-shift settings, and use a test range that covers a range of no less 
than 128, corresponding to a total 180 degrees of clock offset. This does not imply that 128 
phase-shift values must be tested; increments of 4 (52, 56, 60, etc.) correspond to roughly 
one DCM tap, and consequently provide an appropriate step size. Additionally, it is not 
necessary to characterize areas outside the working phase-shift range. 
At the edge of the operating phase-shift range, system behavior changes dramatically. In 
eight phase-shift settings or less, the system can transition from no errors to exhibiting 
errors. Checking the operational edge at a step size of two (on more than one board) refines 
the typical operational phase-shift range. Once the range is determined, choose the 
average of the high and low working phase-shift values as the default. During the 
production test, Xilinx recommends that you re-examine the working range at corner case 
operating conditions to determine whether any final adjustments to the final phase-shift 
setting are needed. 
You can use the FPGA Editor to generate the required test file set instead of resorting to 
multiple PAR runs. Performing the test on design files that differ only in phase-shift setting 
prevents other variables from affecting the test results. FPGA Editor operations can even 
be scripted further, reducing the effort needed to perform this characterization.