Chapter 2 - Hardware Installation
2-52
Clocking
To be able to work with the network connected to the MCU you need to 
synchronize the system clock with the network clock. This is done in two 
steps:
Selecting the network type according to which the system clock will 
synchronize. Only one system type may be selected for clocking. The 
clock source is then defined in the “system cfg”.
Selecting the spans of the selected network that will act as Master and 
Backup clocks. The Master and the Backup clock must be set on spans of 
the same network type.
For more details regarding the clocking setup, see the MGC+ Administrator’s 
Guide, “Clocking” in Chapter 5.
You have completed the hardware installation. The next step in the 
installation procedure is to install the MGC+ Manager software. For more 
information, refer to the MGC+ Administrator’s Guide, Chapter 2.