Locate and mark the center point of the venting pipe. Using a nail 
on the underside of the roof and drive this nail through this center 
point. Make the outline of the roof hole around this center point.
NOTE:  Size of the roof hole dimensions depend on the pitch of 
the roof. There must be a 1 inch clearance (25 mm) to the 
vertical pipe sections. This clearance is to all combustible 
material. 
Cover the opening of the vent pipe and cut and frame the roof hole. 
Use framing lumber the same size as the roof rafters and install the 
frame securely. Flashing anchored to frame must withstand high 
winds. The storm collar is placed over this joint to make a water-
tight seal. Non-hardening sealant should be used to completely seal 
this flashing installation.
Determining Minimum Vent Height Above the Roof.
WARNING:  Major  U.S.  building  codes  specify  minimum 
chimney and/or vent height above the roof top. These minimum 
heights are necessary in the interest of safety. These specifica-
tions are summarized in Figure 59.
Figure 59
Note that for steep roof pitches, the vent height must be increased. 
In high wind conditions, nearby trees, adjoining roof lines, steep 
pitched roofs, and other similar factors can result in poor draft, 
or down-drafting. In these cases, increasing the vent height may 
solve this problem.
Figure 60
When terminating the vent cap near an exterior wall or overhang, 
maintain minimum clearances as shown in Figure 60.
General Maintenance
Conduct  an  inspection  of  the  venting  system  semi-annually. 
Recommended areas to inspect are as follows:
1.  Check areas of the venting system which are exposed to the 
elements  for  corrosion.  These  will  appear  as  rust  spots  or 
streaks and, in extreme cases, holes. These components should 
immediately be replaced.
2.  Remove the cap and shine a flashlight down the vent. Remove 
any bird nests or other foreign material.
3.  Check  for  evidence  of  excessive  condensate,  such  as  water 
droplets forming in the inner liner and subsequently dripping 
out at joints. Condensate can cause corrosion of caps, pipe and 
fittings. It may be caused by having excessive lateral runs, too 
many elbows and exterior portions of the system being exposed 
to cold weather.
4.  Inspect joints to verify that no pipe sections or fittings have been 
disturbed and, consequently, loosened. Also, check mechanical 
supports, such as wall straps or plumbers’ tape for rigidity. 
Venting terminal shall not be recessed into a wall or siding.
A removable panel or other means must be provided in the enclosure 
for visual inspection of the flue connection.
NOTE: This also pertains to vertical vent systems installed on the 
outside of the building.
Slide the vertical vent cap over the ends of the vent pipe and secure. 
See Figure 61.
Installing the Vent System in a Chase
A chase is a vertical box-like structure built to enclose the gas 
appliance and/or it’s vent system. Vertical vent runs on the outside 
of a building may be, but are not required to be installed inside a 
chase.
H
X
12
VENT CAP
GAS VENT
LOWEST
DISCHARGE
OPENING
ROOF PITCH IS X/12
H (Min.) - Minimum height from
roof to lowest discharge opening
ROOF PITCH
H (Min.)
Flat to 6/12
12" (305 mm)
6/12 to 7/12
15" (381 mm)
Over 7/12 to 8/12
18" (457 mm)
Over 8/12 to 16/12
24" (610 mm)
Over 16/12 to 21/12
36" (914 mm)
VERTICAL TERMINATION