This chapter describes the pre-installation considerations, guidelines and procedures needed to
install a 5100/6100 VDR.
Warning. Vpacket strongly recommends that you read this chapter and all installation
procedures prior to installing a 5100/6100 VDR.
You can install a 5100/6100 VDR in three different places:
•
•
On a desk or tabletop
•
On a prepared wall
•
In a 19-inch rack
Before you start installing 5100/6100 VDR units, Vpacket Communications, Inc. strongly
recommends that you develop and review a site plan for your installation. This site plan should
include information such as:
•
•
Location(s) where each 5100/6100 VDR will be installed
•
How the 5100/6100 VDR unit(s) will be physically placed in the facility
•
Configuration parameters required for each 5100/6100 VDR in the installation
•
Any additional equipment required to complete the installation
Determining this information in advance simplifies the installation process.
Note. With front panel LEDs and rear panel connectors, you need to ensure easy
access to the front and back of the unit. Avoid routing any UTP cabling used to
connect to the unit’s ports near power lines, fluorescent lights, or other sources of
electrical noise.
You will find the serial number on the back panel of the unit between the WAN and LAN ports.
The serial number is also present on the main product label on the bottom of the unit.
The serial number is also present on the main product label on the bottom of the unit.