Bunn GMB-PS 사용자 가이드

다운로드
페이지 24
Page 21
SERVICE (cont.)
27479 091596
DIGITAL TIMER (Late Models)
ON
OF
F
ST
AR
T
P2267
LATE MODELS
FIG. 16 DIGITAL TIMERS
Location:
The timer is located inside the hood, attached to
the left side.
Test Procedure.
NOTE: Do not remove or install wires while timer board
is installed. Pressure applied to one side may cause
damage to the board.
1. Disconnect the brewer from the power source and
remove the front access panel.
2. Remove  the  two  #8-32  screws  securing  circuit
board to the mounting bracket.
3. Remove circuit board and spacers (as required).
4. With a voltmeter, check the voltage across termi-
nals TL1 and TL2 when the "ON/OFF" switch is in
the "ON" position. Connect the brewer to the power
source. The indication must be:
a) 120 volts ac for two wire 120 volt models and
three wire 120/208 volt or 120/240 volt models.
b) 200 to 240 volts ac on two wire 200 volt or 240
volt models.
5. Disconnect the brewer from the power source.
If voltage is present as described, proceed to #6.
If  voltage  is  not  present  as  described,  refer  to  the
Wiring  Diagrams  and  check  the  brewer  wiring  har-
ness.
6. With a voltmeter, check the voltage across termi-
nals TL1 and TL4 when the "ON/OFF" switch is in
the "ON" position. Connect the brewer to the power
source. The indication must be 0 volts.
If voltage is as described, proceed to #7.
If voltage is not as described, disconnect the brewer
from the power source and replace the timer.
7. With a voltmeter, check the voltage across termi-
nals TL1 and TL4 when the "ON/OFF" switch is in
the "ON" position. Connect the brewer to the power
source and press the "START" switch. The indica-
tion must be as follows:
a) 120 volts ac for two wire 120 volt models and
three wire 120/208 volt or 120/240 volt models.
b) 200 to 240 volts ac on two wire 200 volt or 240
volt models.
If voltage is present as described, the brew timer is
operating  properly.  Reset  the  timer  as  required,  to
obtain the desired brew volume.
If voltage is not present as described, disconnect the
brewer from the power source and replace the timer.
Removal and Replacement:
1. Remove  the  two  #8-32  screws  securing  circuit
board to the mounting bracket.
2. Remove circuit board and spacers (as required).
3. Remove all wires from the timer.
4. Attach  all  wires  to  the  replacement  timer  board
prior to installation to the component mounting
bracket.  Refer to FIG. 17 when reconnecting the
wires.
5. Install  new  circuit  board  with  spacers  (as  re-
quired) to the component mounting bracket.
6. Adjust the timer as described below.
Timer Setting:
NOTE: Prior to setting or modifying volumes, check
that the brewer is connected to water supply, the tank
is properly filled, and a funnel and server are in place.
NOTE:  All  volume  settings  must  be  done  with  the
sprayhead installed.
1. Modifying brew volumes. To modify a brew vol-
ume, first check that the SET/LOCK switch is in the
"SET" position on the circuit board.