  Technical Specifications 
Mounting Requirements  ▀   
 
ASR 5000 Installation Guide  ▄  
 
   
261 
Mounting Requirements 
Each 24.5 in. (62.23 cm.) height chassis requires 14 Rack Units (RUs) of space. You can mount the system into any 19-
inch (482.6 mm) equipment rack or telco cabinet with the mounting brackets supplied with the chassis. Additional 
hardware (not supplied), such as extension brackets, may be used to install the chassis in a standard 23-inch (584.2 mm) 
cabinet or rack. Both front and mid-mount installations are possible, depending on the position of the mounting brackets 
on the chassis. 
You can mount a maximum of three ASR 5000 chassis in a 2- or 4-post equipment rack or telco cabinet, provided that 
all system cooling and ventilation requirements are met. Three stacked chassis will occupy a minimum of 42 RUs. 
Caution:
  When planning chassis installation, ensure that equipment rack or cabinet hardware does not hinder 
air flow at any of the intake or exhaust vents. Also, make sure that the rack/cabinet hardware, as well as the ambient 
environment, allow the system to function within the required limits. For more information, refer to Environmental 
Specifications
 in this guide. 
Rack mounting requires the use of industry-standard (EIA-310-D, IEC 60297) equipment racks and cabinets, as well as 
supplier-recommended fasteners. The following figure depicts how three chassis can be mounted in a 42 RU equipment 
rack.