Updating to X8.2.1
Cisco TelePresence Video Communication Server Software Release Notes (X8.2.1)     
Page 21 of 32
Upgrade instructions
 
When maintenance mode is enabled on a VCS, existing calls passing through that VCS may be dropped. 
We recommended that you upgrade VCS components while the system is inactive.
 
Early field trial customers who have configured a previous X8.1 or X8.1.1 system for external XMPP 
federation must reconfigure their XMPP federation settings after upgrading to X8.2.
If you are upgrading a VCS that uses clustering, device provisioning (Cisco TMSPE) or FindMe (with Cisco 
TMS managing VCS), you must follow the directions in VCS Cluster Creation and Maintenance Deployment 
Guide
 for X8.2.1.
Follow the procedure below for upgrading VCS to X8.2.1, only if all of the following apply:
 
The VCS is not part of a cluster
 
Device provisioning is not in use
 
Cisco TMS is not managing the VCS
 
VCS is currently running X5.1.1 or later
To upgrade a VCS:
 1.  Backup the VCS (
Maintenance > Backup and restore
).
You should backup your system before upgrading. If you later need to downgrade to an earlier release you 
will have to restore a backup made against that previous release.
If your system was delivered with X6.1 pre-installed, you must make some configuration changes before 
using the backup process as described in the section below.
 2.  Enable maintenance mode.
Log in to the VCS as admin (SSH or serial), and at a command prompt, type:
xConfiguration SystemUnit Maintenance Mode: On
Note that from X8.1 you can enable maintenance mode via the web interface (
Maintenance > 
Maintenance mode
).
 3.  Wait for all calls to clear and registrations to timeout.
 
If necessary, manually remove any calls that do not clear automatically (
Status > Calls
, click Select 
all and then click Disconnect).
 
If necessary, manually remove any registrations that do not clear automatically (
Status > 
Registrations > By device
, click Select all and then click Unregister).
 4.  Upgrade and restart the VCS (
Maintenance > Upgrade
).
Note that when upgrading to a new major release, for example from X7.n to X8.n you need to supply a 
valid release key as a part of the upgrade process.
The web browser interface may timeout during the restart process, after the progress bar has reached the 
end. This may occur if the VCS carries out a disk file system check – which it does approximately once 
every 30 restarts.
The upgrade is now complete and all VCS configuration should be as expected.
Upgrading VCS Control and VCS Expressway systems connected over a traversal zone
We recommend that VCS Control (traversal client) and VCS Expressway (traversal server) systems that are 
connected over a traversal zone both run the same software version.