Installing the 3G4000
4
CONNECT 24 Enrolment Information
Only authorized dealers can enrol a 3G4000 with CONNECT 24. Dealer application forms and additional
information on the CONNECT 24 Voice Response Unit (VRU) can be found at the CONNECT 24 website
www.connect24.com. Please contact CONNECT 24 at the number below for assistance:
USA 1-888-251-7458 CANADA 1-888-955-5583
NOTE: Step 1 should be performed before turning on the 3G4000 unit.
NOTE: Before inserting or removing the SIM card, please ensure the unit is turned off.
STEP 1 - Initialize the 3G4000 with Connect 24
VRU Enrolment
Call the VRU at the toll-free number: 1-866-910-3865. Follow the voice prompts and enter your profile
number, installer ID number, installer PIN number and SIM number. Ensure that all information is
available and at hand before calling the VRU. It is recommended that the radio initialization be
performed at least 24 hours in advance of installation to ensure SIM activation will be complete.
WEB Enrolment
If you have credentials for www.connect24.com, you may also initialize the 3G4000 via the web. Please
check with your Connect 24 Master Reseller or Connect 24 Customer Service for more details.
STEP 2 - Determine the Best Signal Location
1. Remove the front panel.
2. Fit the 3G antenna [2]. Ensure the 3G antenna mounting hardware is fastened securely [3].
3. Attach the 3G radio module with the 3G antenna connector. Ensure that the connector is secure.
4. Turn on the 3G4000 and check the signal strength.
4.1 Connect the battery connector.
4.2 Connect the DC power source to +/- 12V terminals.
5. Allow the unit to power up.
NOTE: The green LEDs will indicate the signal strength. The bottom green LED must be ON for
the location to be acceptable. Please refer to the ‘Status LEDs’ section for more information.
6. Power down the 3G4000 by removing the DC power source and battery leads.
STEP 3 - Connect the 3G4000
1. Using the cabinet, mark the four screw locations. Drill the anchor screw holes.
NOTE: Check for cable conduits and water pipes before drilling.
2. Using anchor screws (not provided), mount the cabinet to the wall.
3. Run the cables through the cable entry [13] or through the cabinet knockouts.
4. Complete the connections on the terminal blocks [11].
NOTE: Ensure that power and Telco circuit connections are made only after the cabinet has been
secured to the building or structure, and has been connected to the protective earth ground.
Descriptions of the terminals can be found in the ‘Connecting the 3G4000’ section.
5. Reattach the front cover [1] securely to the cabinet
.