HQ -ALK-AA-01 HQ-ALK-AA-01 사용자 설명서
제품 코드
HQ-ALK-AA-01
Page 3 of 5
4. Service Output
Test conditions: -- temperature at 20
±2
℃,
-- test to be carried out within 60 days after production data.
Discharge Conditions
Average Minimum Discharge Time
Standard
Discharge
load (Ω)
Discharge
Time
E.P.V.
(V)
New Battery
After 12 moths
at room temp
IEC
43
4h/d
0.9
90 h
81 h
IEC
10
1h/d
0.9
18 h
16 h
IEC
3.9
1h/d
0.8
6.5 h
5.8 h
IEC
24
15s/min, 8h/d
0.9
45 h
41 h
IEC
Drain
1000mA
10s/min, 1h/d
0.9
300 cycles
270 cycles
Satisfaction Standard:
1) 9 pieces of battery will be tested for each discharging standard;
2) The result of the average discharging time from each discharging standard shall be equal to or
more than the average minimum time requirement; no more than one battery has a service
output less than 80% of the specified requirement.
3) One re-test is allowed to confirm the previous result.
5. Electrolyte Leakage Proof Characteristics
Item
Condition
Period
Requirement
Acceptance
Standard
Over-discharge
Characteristics
10Ω continuous
discharge at temperature
20±2
℃; relative humidity:
60
±15% RH
48
hours
N = 9:
Ac = 0;
Re = 1
Storage
Characteristics
Storage at temperature
60±2
℃; relative humidity
below 90
% RH
20
days
There shall be no
deformation exceeding
the specified
dimensions, nor
leakage recognized by
human eye.
N = 30:
Ac = 1;
Re = 2
Alkaline Battery LR6/AA
6. Safety Characteristics
Item
Condition
Period
Requirement
Acceptance Standard
Short-circuit
Characteristics
At temperature
20±2
℃
24 hours
No explosion
allowed
N = 5:
Ac = 0; Re = 1
Incorrect
Installation
4 pcs in series with 1
pc reverse polarized
(IEC60086-5)
24 hrs or till
battery casing
temp reaches
room temp
No explosion
allowed.
N = 4 x 5: