HP Performance Optimized Data Center (POD) 40c 빠른 설정 가이드

다운로드
페이지 41
 
Site requirements  10 
Top view clearances shown 
 
 
Side view clearances shown 
 
Adequate space around the HP POD 40c G2 is necessary for airflow and cooling purposes. 
These minimum clearances provide room for door opening only. Consider additional space as necessary for 
your site. 
 
Safety and clearance area 
  
 
WARNING:
  Check for electrical distribution and transmission lines in, over, and under the 
construction site and maintain a safe working clearance from energized electrical lines. Consult 
your local utility company or AHJ for required clearances.