YP7999A1000 CONTROLINKS™ FUEL AIR RATIO CONTROL PANEL
66-2060—01
2
Approvals
Components are individually approved by the nationally rec-
ognized agencies. Please see component literature for 
details. The panel has UL 508A flame control panel 
approval. Panel is assembled and wired to the UL Stan-
dards.
INSTALLATION
When Installing This Product…
1. Read these instructions and the appropriate product lit-
erature carefully. Failure to follow them could damage 
the product or cause a hazardous condition.
2. Refer to the installation manuals and wiring diagrams 
provided with this panel for the embedded products.
3. Check the ratings given in the instructions and on the 
product to make sure that the product is suitable for your 
application.
4. Installer must be a trained, experienced combustion ser-
vice technician.
5. Disconnect the power supply before beginning installa-
tion to prevent electrical shock and equipment damage. 
More than one disconnect may be involved.
6. All wiring must comply with the National Electric Code 
(NEC) and any applicable local electrical codes, ordi-
nances and regulations.
7. After installation is complete, check out product opera-
tion as provided in the appropriate product installation 
instructions.
WARNING
Fire or Explosion Hazard. Can cause severe injury, 
death or property damage.
To prevent possible hazardous burner operation, verify 
safety requirements each time a controller is installed 
on a burner.
WIRING
WARNING
Electrical Shock Hazard. Can cause serious injury, 
death or equipment damage.
Disconnect the power supply before beginning wiring 
to prevent electrical shock, equipment and control 
damage. More than one disconnect may be involved.
Ground Connection
Earth ground is required for proper operation of the 
ControLinks system. The earth ground must be capable of 
conducting enough current to blow the fuse or breaker in the 
event of an internal short. Ensure the panel is bonded to a 
substantial earth ground. Make sure that mechanically 
tightened joints along the ground path are free of 
nonconductive coatings and protected against corrosion on 
mating surfaces.
Electrical Connections
1. Refer to the appropriate product data sheet for details.
2. Wire size and length will vary, depending on the compo-
nent. Refer to the component literature for specific wire 
lengths, sizes and type recommendations.
3. Wire according to specifications, following all local ordi-
nances and requirements.
4. Field knockouts are required for the wiring. When drill-
ing holes, take care to protect the electronics from metal 
pieces and debris. 
IMPORTANT
Run line voltage and low voltage wiring in separate 
conduit to avoid signal interference. 
Carefully check field wiring and terminal designa-
tions in this document and the associated wiring dia-
gram. They are different from those of the individual 
components.
Panel Inspection
After mounting and wiring, but before powering the panel, 
inspect all internal panel wire connections. Each panel is fully 
tested at the factory; however, wires may loosen during transit. 
Verify that all internal wire connections are secure from the 
Q7999 subbase to the components mounted on the door and 
the S7999D touchscreen interface.
Final Wiring Check and Static 
Checkout
All wiring shall be in accordance with the National Electric 
Codes (NEC) and local electrical codes.
1. Check the power supply circuit. The voltage and fre-
quency must match the specification listed.
2. Check wiring terminations and routing to ensure proper 
connections.
3. Follow any system checkout recommendations for indi-
vidual components as found in the component literature.
4. Restore power to the panel.
CAUTION
Test each limit and interlock to ensure system 
operates correctly as defined in the 7800 Series 
“Checkout and Test” document (Form #65-0229).
WARNING
Explosion and Electrical Shock Hazard. 
Can cause serious injury, death or equipment 
damage.
1. Close all manual fuel shutoff valves before starting 
these tests.
2. Use extreme care while testing the system. Line voltage 
is present on most terminal connections when power is 
on.
3. Replace all limits and interlocks that are not operating 
properly. Do not bypass limit and interlocks.