ADIC SNC 5100 사용자 설명서

다운로드
페이지 228
SNC 5100 
22
Installation Procedure
6-00020-02
 11
Configure the Ethernet Port (Host Name, 
Address, Routes, reboot).
Observe Ethernet Link LED.
If you are using the ADIC Management 
Console, you must configure an Ethernet 
environment.
For more information, see the ADIC 
Management Console User Guide
Configure the Ethernet Port using 
information in Step 6 in Table 2: 
Pre-Installation Checklist. 
If the Ethernet Link LED is not on, go to 
“Ethernet MAP” on page 69.
 12
Issue 
hostTypeShow
 command from 
the service terminal to view host type 
settings for the Fibre Channel ports.
If the hosts that will be connected are not 
the type shown, issue 
setHost
 
command from the service terminal to 
set the host type for each Fibre Channel 
port.
 13
Power down the FC host(s).
Connect the FC cables from the FC 
HBA(s) to the SNC 5100.
Power up the FC host(s).
If the FC1 and/or FC2 Connection Status 
LED for the attached host(s) is not on, 
check FC cables. You may have to change 
the polarity of the FC cables. If the 
problem persists, go to “Fibre Channel 
MAP” on 
page 61.
 14
Issue the 
fcShow
 command from the 
service terminal to show the status of the 
FC interface that is installed and 
connected.
Issue 
fcShowDevs
 command from the 
service terminal to show SCSI target 
devices that are connected as seen by the 
Fibre Channel interface.
Look for FW State=Ready for each FC 
interface. If FW State NOT=Ready, go to 
“Fibre Channel MAP” on page 61.
page 129. If all devices are not shown, go 
to “SCSI Channel MAP” on page 50.
Table 3: Installation Checklist
Step
Actions
Comments and References