HIGH ALTITUDE
MANIFOLD PRESSURE ADJUSTMENT
1. 
Turn off manual gas valve.
2. 
Remove manifold pressure tap plug marked “Outlet 
Pressure Tap” from gas valve using 3/16” Allen wrench. 
Install ⅛” NPT x ¼” barbed fi tting.  See Figure #1 
3. 
Connect manometer or gauge to gas valve pressure 
tap barbed fi tting just installed in step 1. Manometer 
should be capable of reading 1 to 15 inches of water 
column. See Figure #2.
4. 
Turn electrical power and gas supply on. Set 
thermostat high enough to start boiler.
5. 
Start boiler.
6. 
Note gas manifold pressure on manometer or gauge. 
Manometer or gauge reading should be 2½ inches 
water column at start up.
7. 
To adjust manifold pressure, remove “Pressure 
Regulator Adjustment Cap” located on gas valve 
to gain access to regulator adjustment screw. Turn 
adjustment screw clockwise to increase pressure and 
counterclockwise to decrease pressure.  See Figure 
#1.
NOTICE
When doing this procedure, place pressure regulator 
cap back in place to obtain correct reading. Not 
putting cap in place gives false reading of manifold 
pressure.
8. 
Adjust manifold pressure to indicated value using 
known gas Btu value and known altitude of installation.  
See Tables #1 and #2 on following pages.
P/N 240009672, Rev. D [06/2013]
50/75/100 MBH               
GAS CONVERSION INSTRUCTIONS                                                         
AND HIGH ALTITUDE MANIFOLD PRESSURE ADJUSTMENT FOR 
ALUMINUM BLOCK BOILERS
Please read these instructions carefully before starting the adjustment or conversion process. These 
changes must be performed by a qualifi ed service agency.
OFF 
ON 
INLET
OUTLET
PRESSURE REGULATOR 
ADJUSTMENT (UNDER CAP SCREW) 
INLET 
PRESSURE 
TAP 
VR8205 
WIRING TERMINALS (2) 
OUTLET 
PRESSURE 
TAP
SUPPLEMENTAL INSTRUCTIONS
DANGER
Before servicing, turn off electrical power to boiler 
at service switch. Close manual gas valve to turn 
gas supply OFF to boiler. Failure to comply will result 
in death or serious injury.
!
  
9. 
Once correct pressure reading is obtained and remains 
steady, shut off boiler at thermostat, shut off manual 
gas valve, and electrical supply. Remove manometer or 
gauge, ⅛” barbed fi tting and replace pressure tap plug.
10. 
Restore electrical and gas supply, restart boiler and 
check for gas leaks using soapy water or a commercial 
leak detector.
11. 
Fill out data on adjustment/conversion label and attach 
to inside left panel of boiler. 
Operate boiler through at least 6 ignition cycles to check for 
proper operation of boiler before leaving job site. 
Figure 1 - Gas Valve Detail
EFFECTIVE DATE SEPTEMBER 1, 2012