Roberts Gorden DAT75 Manual Do Utilizador

Página de 52
D
UAL
A
IR
®
 H
EATING
 
AND
 
COOLING
 U
NITS
 I
NSTALLATION
 O
PERATION
 
AND
 S
ERVICE
 M
ANUAL
10 
SECTION 6: FLUE INSTALLATION
6.1 Flue Installation
The flue must terminate outside of the building. 
Flues and air intakes must be fully sealed and 
correctly sized for the model. Flues should be 
assembled as detailed on Page 10, Figure 4 through 
Page 12, Figure 8
. The joints between the flue 
terminal and the roof or wall must be sealed. If the 
flue passes through a wall or ceiling of combustible 
material, it must be enclosed by a sleeve of non-
combustible material and be separated from the 
sleeve by at least a 25 mm air gap.
Flues and air intakes must be adequately 
supported so that the DualAir
®
 unit does not 
bear the weight of the pipes.
For flue termination See Page 10, Figure 4 through 
Page 12, Figure 8
6.2 Type C
12
, C
32
 & C
62
 Appliance
Room Sealed.
The heaters are designed to be installed as room 
sealed appliances. The flue and air intake are run as 
separate pipes to the concentric wall or roof 
terminal. See Page 12, Figure 8
6.3 Type B
22
 Appliance
The flue must terminate outside the building and be 
fitted with a low resistance terminal.
See Page 10, Figure 4
6.3.1 Air Intake Terminal Cover
For Type B
22
 appliance installations, an air intake 
terminal cover is an available option. The cover is 
scored flat sheet metal that must be bent into shape.
See Page 12, Figure 7
. Remove and retain the 
screws for the air inlet spigot. Use these screws to 
attach the cover in position over the spigot.
Figure 4: Flue and Roof Detail 
6.4 Converting from Top to Side Terminations for 
Flue and Air Intake
1. Remove the control section lower door and 
 for details.
6.4.1 Flue Conversion
1. Remove the inner and outer flue spigots from 
the top. Retain the spigot and internal seal.
2. Disassemble the flue back to spigot "A". See 
. Ensure all seals are still in 
place.
3. Fit 90° bend directly into spigot "A" pointing 
forwards.
4. Cut a 90 mm length from the 360 mm flue that 
was removed.
5. Attach this piece to the 90° bend, then attach 
the inner spigot that was removed.
6.4.2 Air Intake Conversion
1. Remove the flexible hose from the air intake 
spigot.
2. Remove the spigot from the top.
3. Move the blanking plate from the upper panel 
(previously removed) to the top to cover the 
original flue and air intake holes.
4. Refit the upper panel feeding the air intake flex-
ible hose through the upper hole and aligning 
the flue with the lower hole.
WARNING
Fire Hazard
Some objects will catch fire or explode when placed
close to the heater section.
Keep all flammable objects, liquids and vapours the
required distance away from the heater section.
Failure to follow these instructions can result in death,
injury or property damage.
Roof
Flue
Terminal
Metal Sleeve
Masterflash
soaker flashing
or Rain Collar.
Flue
25mm Air Gap to
Combustible Material