Raypak 302B Manual Do Utilizador

Página de 60
43
The stainless steel direct vent cap must be furnished
by the boiler manufacturer in accordance with its list-
ing (sales order option D-15).
Use  only  double-wall  vent  pipe  and  the  special  gas
vent pipes listed for use with category II or IV gas burn-
ing boilers, such as the stainless steel Saf-T vent by
Heat  Fab  Inc.  (800-772-0739),  Protech  Systems  Inc.
(800-766-3473),  Z-Flex  (800-654-5600)  or  American
Metal  Products  (800-423-4270).  Pipe  joints  must  be
positively  sealed.  Follow  the  vent  manufacturer’s
installation instructions carefully.
Direct Vent - Horizontal Through-
the-Wall
Installation
These installations utilize the boiler-mounted blower to
draw combustion air from outdoors and vent combus-
tion products to the outdoors.
The  total  length  of  the  direct  vent  through-the-wall
exhaust vent cannot exceed 40 ft in length for the flue
outlet.  Each  elbow  used  is  equal  to  10  ft  of  straight
pipe. This will allow installation in one of the three fol-
lowing combinations:
40’ of straight flue pipe
30’ of straight flue pipe and one elbow
20’ of straight flue pipe and two elbows
The total length air supply duct cannot exceed the dis-
tances  listed.  Each  elbow  used  is  equal  to  10  ft  of
straight  pipe. This  will  allow  installation  in  one  of  the
three following combinations:
40’ of straight combustion air pipe
30’ of straight combustion air pipe and one elbow
20’ of straight combustion air pipe and two elbows
The flue exhaust direct vent cap is not considered in
the overall length of the venting system.
Care must be taken during assembly that all joints are
sealed properly and are airtight.
The vent must be installed to prevent the potential ac-
cumulation  of  condensate  in  the  vent  pipes.  It  is
recommended that:
1. The vent must be installed with a slight downward
slope  of  not  more  than  1/4  inch  per  foot  of  hori-
zontal run to the vent terminal.
2. The vent must be insulated through the length of
the horizontal run.
For  installations  in  extremely  cold  climate,  it  is  rec-
ommended that:
1. The  vent  must  be  installed  with  a  slight  upward
slope  of  not  more  than  1/4  inch  per  foot  of  hori-
zontal  run  to  the  vent  terminal.  In  this  case,  an
approved  condensate  trap  must  be  installed  per
applicable codes.
2. The  intake  vent  must  be  insulated  through  the
length of the horizontal run.
Common Venting System
Common  venting  of  Category  IV  systems  is  not  al-
lowed.
The stainless steel flue exhaust direct vent cap must
be furnished by the boiler manufacturer in accordance
with its listing (sales order option D-15).
Use  only  double-wall  vent  pipe  and  the  special  gas
vent pipes listed for use with category II or IV gas burn-
ing boilers, such as the stainless steel Saf-T vent by
Heat  Fab  Inc.  (800-772-0739),  Protech  Systems  Inc.
(800-766-3473),  Z-Flex  (800-654-5600)  or  American
Metal  Products  (800-423-4270).  Pipe  joints  must  be
positively  sealed.  Follow  the  vent  manufacturer’s
installation instructions carefully.
Fig. 40: Direct Vent - Horizontal Through-the-Wall
WARNING: No  substitutions  of  flue  pipe  or  vent
cap  material  are  allowed.  Such  substitutions  would
jeopardize the safety and health of inhabitants.